165–215 Jackson Street
Chinatown · San Francisco, CA 94111
-
Nov 1985
A non-bearing metal stud 7 ft hi wall - 14 ft long.
-
1991
The Eureka Theatre Company premiered the first part of Tony Kushner's Angels in America here in May 1991.
-
Feb 1999
Fiber-wrap selected shear walls, add 2 concrete walls for 3le.
-
Jun 2000
Emergency replace of the fire alarm system.
-
Jul 2000
T/i provide small storage mezz comply with ada new partial walls employee lounge new ceiling & light.
-
Feb 2002
Replace fire alarm.
-
May 2004
Construction of dental office to include non-bearing walls/pressured cylander cabnts under seperate.
-
May 2006
Facade repair to include concrete spall repair, painting, deck coating, sealant replacement. no alterations or additions. repair in kind.
-
Feb 2008
Interior refinishing of existing residential tower main lobby and mezzanine. 2 new front entry doors, new floor coverings, new t-24 compliant lighing and relocate fire alarm main control panel.
-
May 2008
Re-paving 550 battery st plaza, including city sidewalk re-paving, replacement of drainage grates and installation of in-grade lighting fixtures, uplighting with be added to existing trees, understory planting with be replaced and automated irrigation system will be instaled, seperate lighting electcal.
-
Mar 2009
1st /fl.office t.i.existing ground floor shell space was demolished under a separate permit. building. new interior partition walls and suspended ceiling to create new medical offices treatment rooms and accessible restrooms (mep under separate permit).
-
Apr 2009
Remove existing corridor swap cooler fan two units cfm. replace with one energy lab 30, 000 cfm. indirect to direct evaporative air handling unit. reconfigure existing electrical, water, condensate and control.
-
Jun 2009
Reroofing.
-
Feb 2018
Fa ti includes: upgrade residential units at 550 battery to meet sound level required by nfpa-72 p.18.4.1 per meeting minutes from 9/13/17. install 378 speakers in sleeping area. readjust speakers in each one and multi bedroom units; n/a maher.
-
Dec 2018
New speaker in every bedroom to meet 75 dba requirement (398 total new speakers).per owner's request this work is done by a diffrent contarctor per previously approved fa permit # 2018-0226-2180.
-
Nov 2023
Voluntarily upgrade structurally to increase capacity of reinf conc transfer bms at lvl 3 in long. direction and reinf conc sw in transverse direction at lvl 3 to 6. str is not being brought into compliance with current code. the objective is collapse prevention at the 475-year eq per asce 41-17.
-
Feb 2024
One unit; rehabilitate existing kitchen and bathroom, no removal of structural walls.
-
Feb 2024
One unit; rehabilitate existing kitchen and bathroom, no removal of structural walls.
-
Feb 2024
Upgrade existing fire alarm devices to be replaced to include manuel pull stations & smoke detectors. existing bells to be replaced with horn/strobes & strobes. units to have 520hz low-frequency audibles installed. fire alarm control panel shall be monitored with a starlink 24v cell gms-sole path communicatio.
-
Sep 2024
Replace existing fencing, repair rellises slats (all work in kind).
-
Aug 2025
One unit: rehabilitate existing kitchen and bathroom. no removal of structural walls.
-
Dec 2025
One unit; rehabiliate existing kitchen and bathroom. no removal of structural walls. install washer and dryer.
-
Feb 2026
Ground floor: t.i. includes the demolition of non-structural partitions & building new non-structural partitions. restrooms & lighting. all new or revised mep, life safety work will be design build & submitted for permit seperately.
-
Apr 2026
Combine two commercial suites 560 and 570 to be used as one commercial space. remodel existing b-occupancy spaces into a single b-occupancy gym, add one new accessible bathroom and shower. add shower and secondary restroom, new hvac system, two meditation rooms, locker room and a laundry closet.
-
Apr 2026
1/f: t.i include interior re-finishes of existing resid. tower main lobby, no change of use occupancy, occ load or egrewss replace in kind new front entry doors. new floor covering and all finishes. all new or revised mep and life safety work will be design build and submitted sepately.
-
Jun 2026
One unit: rehabilitate existing kitchen and bathroom. no removal of structural walls. replace and relocate washer and dryer.
DBI holds 223 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 223. 5 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early residents and the date of the last recorded sale. Submit an update