Metropolitan Life Building
600 Stockton Street
-
1908
Built.
-
July 2, 1908
George A. Fuller company and Raymond granite company contracted for granite work on the Metropolitan Life Insurance building for the Metropolitan Life Insurance company, at $2,500.
-
1909
The first part of the building went up: a small classical temple in the Ionic order with a great interior space, by Napoleon LeBrun & Sons of New York, for the Pacific Coast Head Office of the Metropolitan Life Insurance Company — whose territory ran from California to Montana — founded by the company's vice-president, later president, Haley Fiske. It is an early work of the City Beautiful in the rebuilding after 1906.
-
January 15, 1909
Watson roof company contracted for roofing on a building for the Metropolitan Life Insurance company, at $1,200.
-
1914
Two symmetrical wings, each about 28 feet wide, were added, probably also by LeBrun & Sons.
-
1920–1922
Miller & Colmesnil filled out the Stockton Street blockfront and added the central Ionic portico, whose pediment carries a heroically scaled sculpture group by Haig Patigian.
-
1930
The Pine Street wing was added, designed by Miller & Pflueger.
-
1954
The California Street wing and the garden court were added, by Thomsen & Wilson, with the landscape architect Thomas Church.
-
1974
Cogswell College, the technical college founded by the dentist H. D. Cogswell in 1887, bought the building, renamed it Swig Hall and made it its campus.
-
1976
Cogswell College, one of two sites to which the 1976 Conference on Violence Against Women was moved at short notice; 1,300 people attended.
-
February 19, 1976
Cogswell College, which had moved from the Mission about two years earlier, occupied less than half of the building and rented most of it to commercial tenants.
-
1982
As Cogswell College, the building was rated '4' in the city planning department's 1976 architectural survey and 'A' — the top grade — on the Foundation for San Francisco's Architectural Heritage final evaluated list of December 1, 1982.
-
1984
Designated San Francisco Landmark No. 167, Metropolitan Life Insurance Company Pacific Coast Head Office.
-
Sep 1984
Alteration of existing building into 350 room hotel.
-
Nov 1988
Demolish & remove all interior improvements.
-
Mar 1991
Rev to 8410225s relocate partition, ti work.
-
Jun 2005
Modify existing chilled water plant to expand with addition of pure comfort cogeneration system.
-
Sep 2005
Conver guestrms to ada compliant guestrms, hearing impaired, add doors, all inerior.
-
Feb 2006
Floor 2 to 8 - upgrade handicap rooms (20) for mobility and ada visual.
-
Mar 2006
Tenant imporvement, re-configure doors & windows to office, new ceiling tile & ligh fixture, new paint, carpet, mirror & moulding.
-
Mar 2011
Level #1-structural infill of existing pool & whirlpool in order to create an "exercise room" (assembly) occupant load verif. new flooring, paint, mirrors, lighting & power for cardio equipment. all existing partitions & ceiling and decorative trims to remain. field verify exit signage and emergency lighting.
-
Jun 2011
Restaurant dining room. remodel existing bar and dining room and constructon of new bar and dining room. no kitchen work.
-
Jun 2011
Lobby lounge renovation- demolition existing bar and pantry millwork and build new bar and pantry cabinets. no exterior work.
-
Sep 2011
Fire sprinklers only on the 1st floor. relocate 50 heads, add 5 heads, plug/remove 4 heads.
-
Apr 2015
Lobby level - demolition existing millwork. install new millwork. repair drywall, install new carpet, remove existing barriers and replace with ada doors maher -not req'd.
-
Dec 2015
Voluntary replacement of fire alarm sys & supplental notificaiton upgrad. "like to like fire alarm sys replacement per csfm information bulletin date 9/4/08". "there is no record plan or ul cert for the existing fire alarm systm".
-
Dec 2015
Interior renovation of an existing retail shop within ritz carlton including mechancial & electrical. n/a maher ordinance.
-
Jul 2017
Replace existing cold rooms with same foot print using prefab factor manufactured modular equipment. mechanical is pre charged systems top mount not to exceed 400 lbs. per cut. 4 boxes @ 592 sq ft. n/a for maher.
-
Sep 2017
Level 1 -3 massage rooms in existing space. 4 mini pedicure area.
-
Aug 2018
Renovation of existing 17, 000 sq ft. courtyard. construction of new 3, 093 sq ft pavilion. **maher n/a**.
-
Aug 2018
T.i. to exisiting restaurant new finishes.
-
Nov 2023
Minor interior remodel of existing restaurant (3528 sq ft) and lobby lounge (1757 sq ft) including hvac, plumbing, electrical.
-
Apr 2026
Minor interior remodel of existing lobby lounge/bar (1227 sq ft) on 4th floor (entry level). includes plumbing and electrical. no exterior work.
-
Jun 2026
Minor interior remodel of existing retail shop. inlcudes plumbing, hvac, and electrical. no exterior work.
DBI holds 86 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 86. 21 of them are nominal $1 street-space or sidewalk permits. 3 expired or cancelled permits are not shown. The 1985 draft environmental report that noted these ratings files the address under Assessor's Block 256; the parcel is on Block 257.
Nearby
- 530 Stockton Street Same street
- 601 Stockton Street Same street
- 626 Pine Street Same block
- 20–24 Vinton Court Same block
- 531–545 Grant Avenue Same block
- 717–719 California Street Same block
- 790 California Street Around the corner
- 16–18 Joice Street Around the corner