734–752 Vallejo Street
Chinatown · San Francisco, CA 94133
-
1950–1965
The city's survey names Keystone Korner at this address among the bars, cafes, bookshops and clubs of the North Beach Beat scene, whose period of significance it sets at about 1950 to 1965.
-
Jan 1983
To receive "final inspection" fix work performed with permit.
-
Dec 1983
Install wall for grocery only.
-
Jan 1984
Proposed new chinese restaurant from.
-
Mar 1984
Install aaawning at 75a vallejo.
-
Oct 1984
Awning to be installed over sidewalk.
-
Nov 1985
To bring into code.
-
Jul 1986
Replace 2 existing with new aluminum windows.
-
Jul 1986
Modify existing corner storefront.
-
Jun 1987
Replace hood over steam table, wok & cooktop, install n/oven.
-
Aug 1988
Reroofing.
-
Sep 1988
Repair fire damaged wall, clg., doors in room #17 & #18.
-
Oct 1989
Re - roofing.
-
Jun 2001
Reroofing.
-
Jan 2002
Roof.
-
Dec 2002
Comply with residential hotel sprinkler ord 170-02 for 2nd and 3rd floor.
-
Aug 2003
Install fire alarm system.
-
Aug 2004
Refurbish existing bathroom on 3rd floor - comply with h.i.s. n.o.v. #200451981.
-
Feb 2009
Install ul 300 fire suppression system.
-
Jul 2016
Change of use from retail to office.
-
Oct 2016
Retrofit gr fl and basement for wood frame seismic retrofit residential program per 2012 int existing building code iebc appendix a4.
-
Oct 2016
20 % ada improvement due to retrofit gr fl commercial and basement level for wood frame program. renovate existing 1 restroom at 752 vallejo and 2 at 750 vallejo to meet ada standard maher not req.
-
Oct 2016
20 % ada improvement due to retrofit gr fl commercial and basement level for wood frame retrofit program. renovate existing restroom @ 752 vallejo and 2 restrooms at 750 vallejo to meet ada standard. add automatic door opener at 750 vallejo.
-
Apr 2023
Rev to permit application 2016-1026-1225 & 2023-0301-2880; to install a rolling gate at 750 vallejo st. entrance the gate is same 752 vallejo st.
-
Apr 2026
Recommencement and completion of work approved under permit application 201610261225 & 201610261226.
-
Aug 2026
Tenant improvement-remove and replace finishes, new stairs, new lighting, new plumbing fixtures, new partition walls, new equipment and mechanical systems. barrier removal to storefront and improved accessible path of travel.
DBI holds 37 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 37. 1 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update