965–985 Geneva Avenue
Excelsior · San Francisco, CA 94112
-
1928
Built.
-
1928
A cinema was built here in 1928 and was known for decades as the Amazon, serving the Crocker-Amazon and Excelsior neighbourhoods. About forty-three feet tall, its lobby on Geneva Avenue and the auditorium set behind the shops. Latterly the Apollo, it closed in 1987 and was used for a time as a church.
-
Jul 1986
Pour concrete pads to provide level area for chairs.
-
Oct 2001
Add 9 antenas to exist building, and radio equipment on the lower roof.
-
Dec 2001
Street space permit.
-
Sep 2002
Install six new antennar mounted within simulated.
-
Feb 2003
Addition/alt to exist theater structure as follows, horiz addition of 434 sq ft on gr floor, rmv exist mezz.
-
Dec 2003
Tenant improv. incl new partitions, doors, millwork, finishes.mechanical, electrical, plumb, & lighting.
-
Jul 2004
Installation of cellular telephone equipment on roof of existing bldng.
-
Sep 2004
Fully sprinkler g/f and mezz floor new system shall tie in to existing main and riser.
-
Nov 2005
Approx. 2, 338 sq ft. of existing second floor shell space to create a new medical clinic.
-
Jan 2006
Mechanical work: ref to permit application 200511218703, ti for existing 2nd fl shell to med clinic val @$245, 000.
-
Jul 2006
Installation of (1) new equipment cabinets to an existing rooftop on a commercial rooftop and eight coax to operate equipment on existing cellular facility.
-
Aug 2006
Install on micro psnez antenna mounted on existing building. roof top exterior behind frp enclosure, painted to match building. install two microcell cabinets at two level.
-
Jan 2007
Install radio equipment in existing building 2nd floor isntall panel antennas on roof top inside shealth enclosure install battery system for equipment.
-
Jul 2010
At&t. a modification to an existing unmanned telecomunication consisting of installing one new umts cabinet, 3 new rrv's, one new run of fiber, new dc power run, 6 (n0 runs of coax, 6newrets, 1newpbc-02 power cabinet and battery back up. 1 new ret cable, remove & replace 3 existing antennas, with 3newantenna.
-
Jun 2011
Add 3 antennas on new triped mounts inside new rodomes. relocate 2 casting antennas. add 6 rrv's & 3 surge suppressors. add 1 rba cabinet, 2 purcell cabinets, 3 rrvw's, new pbc-oz backup a new gps antenna onto an existing platform.
-
Nov 2011
Power wash facade & soffits, new checkpoint, frame mounted, new fixtures at checkout including cosmetic checkout, new finish end panels, new kiosks, new open air cooler, new cafe with endstand, remove photo dept, new triple bowl, sinks, restrooms thorough cleaning & paint.
-
Aug 2015
At&t: modify existing wireless facility to install new purcell with newdus41 & newxmv inside; r&r (3)existingrruw-01 with existingnewrrus-11 with (3)newa2 modules, r&rexistingexisting ucp2 surge suppressors with existingnewdcg surge suppressors; r&r (6) antennas with (6)newantennas; r&r(6)existing radomes with (6)newradomes; remove (6)existingrruw-01.
-
Feb 2016
Att: modify existing att facility: install 3new antennas inside 3new 2-" radomes; 3new rrus - 12 units; install 3new rrus-32; reloacte 3existing rrus-11 from equipment to antennas; install 5new tripod antenna pipe mounts; install new duc-41 inside existing parcell cabinet; reloacte existing sector c antenna & equipment.
-
Apr 2017
Att modification: r&r 2existing cabinets & 2 pbc-02; install new dc power plant, 6 new rrus, new dc6, new fiber under, 3 new xmu, 4 new tma; relocate 3 existing rrus. no antenna work.
-
Sep 2020
T-mobile modify e wireless installation. remove & replace three (3) antennas; install three (3) ballast mounts; install three (3) antenna; remove & replace six (6) radios; install two (2) cabinets; install three (3) bb units inside cabinets; install three (3) hybrid cables; install one (1) xmu.
-
Aug 2021
Modification to existing verizon wireless facility. replace 6 antennas, replace 3 rrus, add 3 rrus, replace 3 ovps, add 3 cominers. replace 6 radome cannister and add associated hardware. remove existing coax cable and add 3 hybrid cable.
-
Feb 2022
Remove 9 antennas: install 9 antennas, remove 9 rrus, install 6 rrus, remove 6 frp radomes. install 6 frp radomes, install 3 y cable splitters, install barriers/striping, install 1 baseband, install 2 battery strings, install 1 rectifier.
-
Mar 2022
All new work shall consist of interior partitions, millwork, electrical work, mechanical, plumbing and flooring defined within the documentation and with adherence to the construction documents and specification. the reconfiguration of the space will not cause a change to the occupancy type unless.
-
Apr 2024
Reroofing.
-
Dec 2025
T-mobile: remove 1 existing antenna. install 6 new antennas inside 6 new radomes. remove 1 existing cabinet. install 2 new cabinets. install 12 new batteries. install new 200amp panel.
DBI holds 69 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 69. 3 of them are nominal $1 street-space or sidewalk permits.