August 16, 1961
The Office of the Assessor-Recorder photographed the property for tax assessment. Manning's Bakery was at the address.
-
Feb 1982
Additions alterations or repairs.
-
May 1987
Tenant improvements, carpet, ceramic tile, glass, paint.
-
Mar 1988
New partitions, acoustical, painting, electrical, plumb, demolition/hvac.
-
Sep 1997
Cti 2l me 1st fl.
-
Oct 1997
Cti-2.
-
Jul 1998
One-stop, mechanical dwgs, t-24, hvac, demolition, piping/wiring.
-
Aug 2006
Remove and replace supply fan and ductwork on roof only. chiller and storage tank under separate permit.
-
Sep 2006
Remove/replace existing mechanical rooftop equip. install new chiller, pumps & storage tank. supply fan & rooftop ductwork under separate permit.
-
Jun 2013
Voluntary seismic upgrade. accessibility upgrade of existing common restrooms. improvements of two building entry lobbies. teixant spaces maintenance upgrades.
-
Aug 2013
Voluntary structural strengthening. construction of foundation for one interior steel braced frame and one interior shear wall.
-
Dec 2013
Non structural t.i. walls for office and conference rooms, add unisex bathrooms, open office improvements.
-
May 2014
Mep for 201312194576.
-
Aug 2018
Demolition of non structural partitions, ceiling assembles, doors, frams, hardware, lighting, electrical, millwork, plumbing and finishes. build back of accessible restrooms including non structural paritions ceiling assemblies, doors, frames and hardware. no increase in area, change of use. mep/life sep.
-
Mar 2019
Build back accessible restroomsincluding non structural partitions, ceiling assemblies, doors, frames, hardware, lighting, electrical, plumbing finishes in empty tenant space. no structural work and no change in use, area or occupancy. mep included.
-
Apr 2019
Revision to permit #201808106985, change restroom orientation to reuse existing plumbing chase plus add, full mep engineering. 2nd fl.
-
Jun 2020
Interior tenant improvement including new non-structural partitions, lighting, plumbing, finishes, and millwork. voluntary addition of new sprinklers to 4th floor. no change in occupancy, use, or area.
-
Sep 2020
4/f: t.i., add (247) sprinklers & main lines and fittings to conform to new wall/ceiling layout of the t.i. ref bpa#202006088251.
-
Jan 2021
4th floor - electrical work for ti. ref pa 2020-0608-8251.
-
Jan 2021
4/f: mechanical & plmbing for t.i. on 4/f. ref t.i. permit application 202006088251. maher n/a.
-
Sep 2021
Suite 100: interior t.i.: new millwork, finishes, non-structural partitions, light fixtures. mechanical and electrical included. fire/life safety and sprinkler under sep permit. maher n/a.
-
May 2023
3/f: t.i. includes demolition of non-structural partitions and building new non-stru partitions. all new or revised mep's, sprinklers & alarm life safety work will be designed build and submitted separately (building is fully sprinklered) as part of scope.
-
Jun 2023
3/f: installation of new fire sprinkler system; rlh scope of work starts at the existing top of riser located in stair 1 (st1-3) ref pa 2023-0517-7916.
-
Jul 2023
3/f: mep add branch ductwork and required vavs to new hvac zones, ddc system to be added to the floor, providfe new lighting & power to existing circuit. ref permit application 202305177916.
-
Aug 2024
Abe ord 51-16 accessible building entry upgrades, relocate door actuator to front facade, exterior sidewalk upgrades. abe 20200492108.
-
Dec 2025
1 floor - suite 100: interior ti. including new non-structural partitions, millwork, light fixtures and plumbing fixtures and finishes.
DBI holds 82 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 82. 9 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update