246–250 Sutter Street
Financial District · San Francisco, CA 94108
-
1940s–present
The Metropolitan restaurant traded at this address.
-
Dec 1981
Additions alterations or repairs.
-
Sep 1986
New foundation additions & seismic bracing, elevators, etc.
-
May 1987
Install new partitions, walls floor and ceiling finishes.
-
Oct 1987
New interior ti, partitions, electrical, mechanical, fire sprklr.
-
Jul 1988
Tenant improvement of front portion of 6th fl.
-
Aug 1988
New interior tenant improvement work @ 1st floor.
-
Feb 1997
Cti-1 2/f el me sp.
-
Jan 1999
Oti 1 3rd floor, el & me.
-
Feb 2001
One stop: tenant improvement new mezzanine, ceiling, new lithgnindg, refer to permit application 200102142099.
-
Jan 2003
Interior remodel of existing retail store, no storefront or entry work, minor m, e, p work, ceiling, partit.
-
Feb 2006
Interior tenant improvement. mechanical. under separate permit.
-
Mar 2010
Spec suits 400 & 450-4th.floor. t.i.demolition of non-structural partitions: build newnon-structural partitions.all newor revised hvac, electrical., plumb.& life safety work which will be design build; permit submitted separately. building fully sprinkeled. rest work under this permit.
-
Jun 2010
3rd floor-t.i. includes demolition of non-structural partitions & building new non structural partitions. all new or revised hvac, electrical, plumbing & life safety work will be design build & submitted seperatly. building fully sprinklered. work included common corridor. upgrade restrooms.
-
Jul 2013
5th fl: t.i includes the demolition of corridor and restroom finishes, plumbing fixutres, lighting and life safety and installing new finishes, plumbing fixtures lighting and life safety. all new or revised hvac, electrical and life safety work will be design build and submitted separately. building fully.
-
Dec 2014
2nd floor t.i. includes (demolition of non-structural partitions under permit application 201412022793.) building new non-structural partitions. all new or revised hvac, electrical, plumbing & ls, sprinkler will be design build & submitted separately. (building is fully sprinklered). maher n/a.
-
Apr 2015
2nd floor: mechanical & electrical work for ti - new heat pumos and transfer fans and lighting. ref pa 2014 1218 4012.
-
Aug 2015
6th floor: ti - includes demolition of non structural partitions and building back new non structural partition. all new or revised meps & life saftey & sprinkler work will be submitted under under sep permit. bld is fully sprinklered. maher na.
-
Apr 2016
Ground floor new tenant - inteiror remodeling of approximately 3418 sq ft in a multi-story, multi-tenant existing building. n/a maher ordinance.
-
May 2018
6th fl - ti to include demolition of non-structural partitions. new partitions, mep, life safety under separate permit.
-
Jul 2018
Mep for tenant improvement on the 6th fl. ref permit application 201805148978.
-
Dec 2019
Ti of existing space on basement level that includes non-structural partitions, doors, fixtures, finishes, electrical, mechanical, and plumbing in a mixed-use building. scope includes new studios, offices, restrooms with showers and reception area. maher na.
-
Jul 2022
Ti work for hot 8 yoga with non structural walls, new restrooms, locker rooms, yoga studios, laundry room with associated plumbing, mechanical and electrical.
-
Dec 2025
2/fl- commerical interior ti for soft demolition and build out of non structrual work.
-
Apr 2026
2/f: air distribution for new floor layout. mechanical only. ref 202512121666.
DBI holds 167 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 167. 2 of them are nominal $1 street-space or sidewalk permits.