Built.
-
July 31, 1912
Lincoln and Grant contracted for all work except painting, heating, gas, electric fixtures, shades, wall beds on three-storey and basement frame apartments, then going up, at $3,900.
-
Mar 1992
2 stucco patches on corner of house.
-
Jul 1994
Provide guard pailay at roof.
-
Feb 2003
Repair of loose stucco.
-
May 2003
Respond to nov #200334655, due to obvious deflected, replace entrance & garage header.
-
Dec 2003
Replace windows at two units.
-
Jan 2005
Renew permit app 200407229985 & 200408262655 for final.
-
Apr 2005
Reroofing.
-
Feb 2015
Boiler room fire taped an repair as needed with 5/8 type x drywall. general maintenance clean up. to comply with nov #201415391. clean exterior pathway to rear and sides of building. rekey lock set wrong way, repair radiation in three units. banging noise. top level radiation at top level is pitched.
-
Jun 2017
Comply with complaint 201781191, item 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20.
-
Nov 2017
Replace existing skylight in kind.
-
Oct 2018
To obtain final inspection for work approved under permit application 201706209892. all work is complete.
-
Dec 2019
Soft story retrofit per sfebc chapter 40 engineering criteria 2016 cebc.
-
Jan 2020
Common area: move back center wall in basement 6" x 9' long for new electrical service. comply with nov 201798202. replace damage flue. legalize p-trap in multiple units, verify pto boiler.
-
Feb 2020
Revision to pa 2020-0102-1152 add 7' of center foundation to job.
-
Feb 2020
To comply with nov# 201540621. item #2, repair windows or reinstall new windows hand railing. 201543021 #2, 201540301 #5, #6, #12, 201540241 #2. all windows are not facing street all at back. all repair in kind.
-
Nov 2021
Comply with nov #2015402415, 6, 11, #8 201540621 2, 5, 10. #22015428816, 201540301 1, 5, 7, 12, 13, 15, 16, 18. 201525801, 20154-951/#11 6, 201543021 #12 2, 3, 4, 5, 6, 20145391 5, 6, 7, 12, 13, 14, 17 nov 202060392, nov202060393, nov 202060961.
-
Feb 2024
To obtain final inspection for work approved under permit application 2020-0226-551 and 2021-1122-2959 and 2017-0620-9892. all work is completed.
-
Feb 2024
To obtain final inspection for work approved uynder permit application 2020-0102-1152 and 2020-0205-3572. all work is complete.
2 nominal $1 street-space or sidewalk permits are omitted from the timeline. 5 expired permits are not shown.
Nearby
- 139 Hugo Street Same street
- 1257 2nd Avenue Same block
- 1269–1271 2nd Avenue Same block
- 1251 2nd Avenue Same block
- 1284–1286 3rd Avenue Same block
- 1279 Third Avenue Around the corner
- 1239–1243 3rd Avenue Around the corner
- 1216–1218 3rd Avenue Around the corner