1914
Built.
-
July 10, 1942
Photographed.
-
Jan 1982
Additions alterations or repairs.
-
Jul 1982
Additions alterations or repairs.
-
Jul 1984
Demolish, form, pour new walls, install 2 solarium structures.
-
Jun 1986
Relocate pendant sprinklers on 1st & 2nd floor.
-
Mar 1997
Demoexistingpartit/new partit/revise electrical/me/plg systems/upgrade.
-
May 1998
Modify existing pipe system.
-
Jun 1998
Replace old fire alarm system.
-
Jun 1998
Replace old fire alarm system.
-
Jul 1998
Reroofing.
-
Nov 2013
Install delayed egress magnetic locking system connected to existing fire alarm system.
-
Dec 2013
Provide a delayed egress system and components to existing exit doors at 12 locations on 3 levels per plan.
-
Aug 2016
Demolition of select interior wall to create 18 bedrooms, 16 bath for memory care residence. connect 2 wood frame buildings, connect corridors to e g type 1 main building, build up floors of type 5 building to align with main building, including ramps for level chg, new mechanical, plumb, electrical for new units /2 new stairs.
-
Oct 2016
1st floor: select demolition of unit bathroom, sitting rm, closet, partition wall at activity rm & dining rm. renovate unit into 2 units. 2nd floor: select demolition at stairs, dumbwaiter, recpt and unit bedrm new unit with modification of existing unit. revise prep area at dining. 3rd floor: select demolition at stairs dumb.
-
Oct 2016
Repair cracked/damaged conc columns for the elevator mechanical room at roof level; maher n/a.
-
Feb 2017
Remodel and relocation of existing kitchen, demolish existing kitchen, replace resident rooms and bath into former kitchen space. demolish existing dumbwaiter and renovate existing nurse station. revise stair and closet area for accessible ramp. reuse existing kitchen hood, new duct to roof. maher na.
-
Jul 2017
Install new fire sprinkler system for 2nd and 3rd floor partial floor remodel of retirement facility. ref app#201608155030.
-
Oct 2017
Revision to 201610069700, removel work at 1st fl to add 2 new restrooms, select demolition of walls, celing, doors, repair/paint new finishes to match existing conditions. maher n/a.
-
Nov 2017
Replace existing sign lettering with new illuminated channel letter se5 (name change) maher na.
-
Feb 2018
Like for like for existing system and upgrade to system to accomodate new addition to building. ref app#201608155030 new scope add 18 low freq. horns to new addition. per nfpa 72. n/a for maher.
-
Jul 2018
New evacuation maps to replace existing maps on all floors.
-
Aug 2019
Horizontal addition. 4-story addition located in existing parking lot with 20 rms and 5 parking spaces @ grd floor. 2-story addition community building in courtyard to connect to main building. existing assisted living facility has 79 rms, total rms shall be 99 rms.**comply with maher, route to dph**.
-
Dec 2024
New main switchboard for new pge electricl service and/or upgrade for anticipated mechanical loads which shall introduce new cooling systems.
-
Apr 2025
Installation of 89 packaged ac units including electrical and condensate drainage lines. removal of existing steam heating system. removal of existing steam/hydrant system.
-
Aug 2025
Reroofing: no torch down, no hot works.
DBI holds 38 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 38. 2 of them are nominal $1 street-space or sidewalk permits.