1800–1890 Chestnut Street
Marina · San Francisco, CA 94123
-
1924
A recreation centre opened here in 1924 on the ground of Lobos Square — the 1906 refugee camp that had become a city park — first as the Funston Recreation Center, later Funston Playground, and today the George R. Moscone Recreation Center. It is a contributing building to the California Register-eligible discontiguous Midcentury Recreation Historic District.
-
1953
The Marina Branch Library, built in the early 1950s and designated San Francisco City Landmark No. 262.
-
Jan 2005
Remodel & addition to an existing 6544 gsf library owned by san francisco public library.an addition of.
-
Mar 2006
New fire alarm system-inlcudes one fact, one remote annunciator, one nal panel, tyre sd's one hd, 3 pull stations, four strobes, and 15 horn strobes.
-
Nov 2006
2139 sq ft building addition, site improvments (stairs, ramps, walkways, landscaping, irrigation) seismic upgrade to existing 8493 sq ft byidling, new restrooms, new kitchen, new mechinical equipment and piping, new electrical equipment, wiring & lighting. (sprinkler substitution for 1-hr construction).
-
Feb 2007
As builts to appalication no.2006/03/14/6603: (permit #1082754) remove reference to srpinkler system, rev.sequence to sho fsd's and closure via heat detector.
-
Apr 2007
Overhead fire protection system at existing recreation building. total of 80 heads.
-
Jul 2007
Install basketball backboards and wheelchair lift. deferred approvals for permit application 2006/1103/6879.
-
Dec 2007
New sprinkler monitor system: 1 control panel with dialer, 3 addressible monitor modulus, 1 smoke detector, 1 manual pull station, 1 horn/strobe, 1 sprinkler bell.
-
Mar 2008
Renew permit application 200603146603 for final inspection (fire alarm).
-
Apr 2008
Renew permit application # 200704058099 for final inspection.
-
Apr 2008
As built drawings-fire sprinkler. p/a 200704058099, 200804028625.
-
May 2008
Renew permit application 2007/07/05/6032 for final inspection only.
-
Sep 2016
Renovate an existing playground with new playground work including fencing, paving, planting, irrigation, drainage, installation of play equipment and park furniture project also includes a new dog play area. n/a for maher.
-
Apr 2019
Removal of existing 4" backflow preventer feeding irrigation system to moscone park, reinstall new 4" backflow prelentor feeding irrigation system to moscone park.
-
Jul 2021
Provide waterproofing repairs at southwesr corner's reading area. repair sealant joist btw storefront, brick wall and concrete curb. repoint existing mortar joinst with concave joinst at limited location indicated in the drawing. clean & seal brick with water sealant at all exterior brick.
5 nominal $1 street-space or sidewalk permits are omitted from the timeline.
The library on this parcel is dated twice in the historical record and the two dates do not agree: 1953 in one passage and 1954 in another. Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. The roll classes this parcel as a vacant lot and also gives it a build year of 1900. Two buildings stand on this parcel — a recreation centre of 1924 and a branch library of the early 1950s — while the assessor's roll gives the whole parcel a single build year of 1900. Submit an update