3400 Laguna Street
Marina · San Francisco, CA 94123
-
1925
Built in 1925 as an institutional building, now Heritage on the Marina.
-
Dec 1986
Addition of fire sprinkler system.
-
Apr 1998
Remove emergency generator, replace with larger, new concrete.
-
Apr 1999
Install new fire alarm system all interior work.
-
May 2002
Reroofing.
-
Jun 2013
Remodel basement level resident common use spaces. subdivide existing common use spaces into rooms. fitness center, arts and crafts, wellness center, laundry.
-
Feb 2016
One unit, interior room remodel 0 addition of 70 sq ft. new lighting where occurs. remodel bathroom. minor chane to one egress hallway. sprinkler work under separate permit. maher na.
-
Mar 2016
One unit, interior remokdel (340 sq ft) remokdel existing studio apt and bathroom. upgrade shower, add grab bars with backing, add tile throughout. replace plumbing fixtrues. replace existing lights/add new. add new kitchenette with sink & appliances - no cook top. maher na.
-
Mar 2016
Remodel 4 existing common room kitchens. new countertops, cabinets, flooring, new appliances. refrig, microwave. reduce light fixtures, add new fixtures, replace sinks and faucets. maher not req.
-
May 2016
One unit: interior remodel 330 sq ft remodel existing studio apt. bathroom, upgrade shower add grab bars with backing. add new tile throughout. replace plumbing fixtures, replace existing light fixtures add new kitchenette with sink. no stove. maher na.
-
Sep 2016
1 story horizontal rear addition.
-
Jun 2017
One unit: remodel and expand existing bath. remodel e closet. cosmetic renovations at living area. work includes lighting, casework, finishes, fixtures.
-
Aug 2017
#328- remodel existing bath, kitchenette and closet, cosmetic renovations of living area, work includes new lighting, casework, finishes and fixtures. n/a ordinance #155-13.
-
Aug 2017
Unit merger, combine #244 (1) studio and #242 (1) bedroom units to create (1) two bedroom unit, to be called #244. remodel & expansion of existing bath. remodel of existing closet & cosmetic renovations of living area. addition of kitchenette. work includes new lighting, casework, finishes & fixtures maher na.
-
Feb 2018
One unit: remodel of existing kitchenette and bathroom, and cosmetic renovations of living area. work includes: new righting, casework, finishes, and fixtures.
-
May 2018
Renovation of 2 existing restrooms, scope of work includes replacement of fixtures and fittings in kind and replacement of interior finishes maher na.
-
Sep 2018
Interior renovation of existing cottage building. removal & additional of non-structural partition walls. replacement of 1 exterior ramp & railing & replacement of existing wood fence. maher n/a.
-
Sep 2018
One unit. remodel of existing bath and closet. cosmetic renovation of living area with new lighting, casework and finishes and fixtures. maher n/a.
-
Oct 2019
One unit: remodel of existing bath remodel of existing closet & cosmetic renovations of living area, work includes, new lighting, casework, finishes and fixtures. maher n/a.
-
Jul 2020
4th floor: suites 403 & 404: existing occupancy class r-2.1 property (no change of use) combining two units. cosmetic renovation of existing bathroom, and existing kitchenette at one unit. remodel of existing bathroom at one unit.remodel & expansion of existing bath, remodel expansion of closet at one unit.
-
Jul 2020
2nd floor: suites 204, 205, & 206: existing occupancy class r-2.1 property (no change of use) combining 3 studio units to one (1) 2 bedroom two bathroom unit. renovation includes addition of new kitchenette, cosmetic renovation of existing bath at one unit, nw lighting, casework, finishes, and fixtures.
-
Apr 2022
4th floor: combination of (3) studio units to one (2) bedroom (2) bathroom, unit renovations addition of new kitchenette, cosmetic renovations of new lighting, casework, finished and fixtures.
-
Mar 2023
Replace existing passenger elevator manual cab and hoistway doors with auto sliding doors.
-
May 2024
3rd floor: one unit: remodel and expansion of existing batah, cosmetic renovations of living area work includes, new lighting, casework, finishes and fixtures. no exterior work. no combining units.
-
May 2024
4th/fl- two units to combine two studios units into a 1 bedroom unit. converson of bathroom into a kitchenette. remodel of existing bathroom inlcuding replacing existing lavatory cabinet and sink, mirror and shower toilet to remain.
-
Aug 2024
Revision to permit application 2023-0322-4143 changing the existing elevator cab & scissor gate doors; tracks, hardware. coordinate extent of demolition with new replacement cab. basements, 1st, 2nd & 3rd fl.
DBI holds 145 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 145. 7 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. This building is dated 1925 in the historical record; the assessor's roll gives the parcel a build year of 1924. Submit an update