1936
Listed in the telephone directory as Seiberling Rubber Co Distributor, Thompson Tire Co tires.
-
1953
Listed in the city directory as Perry & Whitlaw auto repair.
-
Mar 1982
Additions alterations or repairs.
-
Oct 1989
Parapet reinforcing.
-
Jun 1995
Wall sign 4' x 18'.
-
Aug 1995
Comply with umb ordinance using special procedure.
-
Oct 1998
Replace existing auto paint booth paint mixing room relocate.
-
Dec 1998
Adding pyro-chem pre-engineered fire system into paint booth.
-
Sep 1999
Handy capp restroom.
-
Jan 2000
Installation of truss system to support roof top exchaust system that was permitted.
-
Nov 2002
Renew appl#9919809 for final inspection.
-
Oct 2007
Interior remodel to create 17 new tenant spaces, add 4000sq.ft. of usable space, new interior egress stairs, 2 common ada bathrooms, 5 private restrooms, replace exterior rollup doors with new doors and windows for tenant spaces, add 19 skylights.
-
Oct 2007
Remodel existing int of building. expand exist 2nd floor within exist building envelope. const int unit egress stair. const int demising walls, remove exist bath and const 2 common assessible baths and 3 private baths. const 24 wet bars. replace exist garage door, street level windows and pedestrian doors.
-
Nov 2007
Remodel interior of existing building, construct interior demising walls, remove existing bathroom & construct accessible bathrooms. no work on exterior of work.
-
Mar 2008
Remove sign and closed orig. permit#9508566.
-
Mar 2008
Renew permit application 2000011940, #9824614, #9820380 for final inspection.
-
Mar 2008
Renew permit application 8919472 for final inspection only.
-
Apr 2008
Change of unit designation from permit application 2007-1019-5974-eight units changed from office to manufacturing. rev. of description from 2007-1019-5974-pa suspended by cp to reduce pdr space. this rev. reallocate pdr space to meet existing conditions.
-
May 2008
Removal of non-structural interior walls, floors & ceilings as well as existing restrooms & electrical equipment prepare for interior remodel, ref #200710195974.
-
Sep 2008
Change freight loading area & storage above to manufacturing units. two new service modules, one for each unit. revision to permit application 200710195974 s1.
-
Jun 2010
Replace stairway in kind, renovate existing ada restroom & install 1 new ada restroom.
-
Jun 2011
Reroofing.
-
Jan 2012
Replace 2-existing roll-up doors, replace 2-existing man doors in-kind. refurbish existing steel framed windows(9). install new hardwood floor. ovelay existing concrete floor. skim coat & paint existing bathroom & stairwell. all work non-structural.
-
Feb 2012
Install new glazed partition wall at mezzanine level, install new section of guardrail at existing stairs. install new private shower, install new slide pole.