224–226 11th Street
Mission · San Francisco, CA 94103
Permit history
-
Jan 1990
Reroofing.
-
Sep 1990
Install three aluminum windows.
-
Apr 1993
Reroofing.
-
Feb 1994
Comply with umb ordinance.
-
Apr 1995
Comply with umb ordinances.
-
Aug 1995
Install moment frame at window openings to replace blocking.
-
Sep 2007
Remodel interior of ex. building, expand ex. 2nd floor over ex. roof. construct interior egress stairs. consruct interior demising walls. remove ex. bathroom and construct 3 ada compliant restroom and 4 ada non-compliant restroom. construct 2 kitchen.
-
Sep 2007
Remodel interior of existing building. add second floor within existing building. envelope. construct new interior egress stairs, new interior demising walls, 3 new bathrooms. create 9 tenant spaces from 1 existing. no change to existing building. envelope. mep and sprinkler plans on separate permit.
-
Sep 2007
Vertical addition: remodel interior of existing building. expand existing second floor over existing roof. construct third floor over existing and proposed second floor. construct interior egress stairs. construct interior demising walls. construct seven bathrooms.
-
Jan 2008
Construct new heating, cooling & fresh-air system within an existing building. construct new electrical system, new fire sprinkler system. ref permit application 200709193104.
-
Jan 2008
Interior non-structural demolition only, no exterior work, ref permit application 200709193104.
-
May 2008
Reroofing.
-
Jun 2011
Revision to pa 2007.09.19.3104. install h.c. restroom and enlarge main entrance, and install new kitchenette.
-
Dec 2011
To obtain final inspection for work approved under permit application 2008110635980. all work is complete.
-
Dec 2011
Renew for final for permit application 200709193104.
-
Dec 2011
To obtain final inspection for work approved under permit application 200801092146. all work is complete.
-
Dec 2011
To obtain final inspection for work approved under permit application 200801303617. all work is complete.
-
Apr 2016
Change of occupancy. install "nfpa 13" sprinkler system (under separate permit). remove gates & install new exterior doors. existing mechanical & electrical system to remain. n/a for maher ordinance no 155-13.
-
May 2016
Install new 4"underground fire service, install new sprinkler system in existing building; maher n/a.
-
Nov 2016
Remove portions of gwb to provide access for electrical & sprinkler work ( separate permit - 201605066756). n/a maher ordinance.
-
Dec 2016
Install 1 new 5 ton split system heat pump and ducting to replace existing system maher na.
-
Mar 2017
Ref f/s system permit application 201605066756: provide fire sprinkler monitor system.
-
Oct 2025
Interior remodel of 224 11th st with 2 punched openings connecting 216 11 st. both spaces to be operated as remedy veterinary specialist. arch, mep plans included. no exterior work or site work except exterior door replacement. fully sprinklered.
-
Feb 2026
Change of use from manufacturing to veterinary clinic. removal of non structural partitions and addition of new partitions for offices/exam and procedure rooms. minimal exterior revisions needed for replacing 2 doors. no overnight boarding or site work. meps & life safety to be deferred.
DBI holds 26 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 26.
Not yet documented: the architect and builder and the early tenants. Submit an update