75 14th Street
Mission · San Francisco, CA 94103
-
1927
Built as an industrial building, recorded as occupied by the Western Cooperage.
-
Sep 1988
Reroofing.
-
Jan 1990
Inject epoxy into cracks in brick walls.
-
Sep 1992
Parapet reinforcing.
-
Jun 2000
Seismic retrofit 104(f) procedure.
-
Sep 2000
Reroofing.
-
Jul 2016
Remove non-bearing partition walls at 1st floor and mezzanine. n/a for maher.
-
Jul 2016
Remodel of existing workshop. per pdr use, new mezzanine shall be no more than 1/3 overall floor area.
-
Aug 2016
Otc alterations permit.
-
Sep 2016
Remodel & conversion of a single pdr workshop to two pdr workshops. addition of new mezzanine new lobby entrance, 4 new accessory offices (750 sq ft total); 2 lunchrooms & 6 bathrooms; replace doors & skylights. ** maher: n/a **.
-
Mar 2017
Reroofing.
-
Jun 2017
Sprinkler waterflow and supervisory system with nw control panel, radio communicator smoke det. above and pull station.
-
Jun 2017
Mezzanine structural related to building pa 2016-0906-6864.
-
Aug 2017
Streetspace.
-
Sep 2017
Rev. to bpa# 201609066864. relocate egress corridor reconfigure bathroom and kitchenette and replace 1 existing solid core door with glazed door, new glazed egress door, new glazed roll up door mep deferred; n/a maher.
-
Feb 2018
Add (36) new sprinklers under new mezzanine floor per nfpa #13. ti #201609066864. n/a maher.
-
Feb 2018
Revision to app#201609066864: enclosed office space at existing mazzanine. n/a for maher.
-
Apr 2018
Replace existing rooftop package units, install bath fans in new bathrooms.
-
Jun 2018
Title 24 light/electrical only. ref 201609066864 maher na.
-
Jan 2019
Tenant improvements to include new non bearing partition walls for workshop and storage spaces. mep and sprinklers to be design build.
5 nominal $1 street-space or sidewalk permits are omitted from the timeline.
Not yet documented: the architect and builder and the early tenants. Submit an update