3326–3340 25th Street
Mission · San Francisco, CA 94110
Permit history
-
Jul 2024
Bathroom remodel, existing locations not moving. bathtub to shower. no walls being moved. approx 100 sq ft.
-
May 2023
Replace 22 windows like for like, retrofit installation. 20 windows are visible from the street and will be fiberglass. two windows in the lightwell will be vinyl. title 24 compliant. same size, same locations, max u-factor 0.30.
-
Nov 2022
Reroofing.
-
Oct 2018
Kitchen and bathroom remodel. maher n/a.
-
May 2014
Kitchen remodel at top floor. counter, new cabinet, same sink. lighting to comply with cec 150(k).
-
Apr 2014
Reroofing.
-
Aug 2005
3r-4282 compliance for condo conversion.
-
Jan 2002
Remodel bathroom and put sheetrock/replace in kind on 2nd floor.
-
Sep 2001
Replace with upgraded in-kind double hung sash assembly. 4 openings living room streetside/5 opening l.
-
Aug 2001
Partial kitchen remodel, add washer/dryer to both one unit -3, 000 to complete.
-
Feb 2000
Kitchen remodeling, add washer and dryer to both units.
-
Aug 1999
Renew appl-9901791 for final inspection.
-
Jan 1999
Repair water damage-wall framing-bathrm, re-sheetrock &tile.
-
Sep 1998
Rebuild existing back steps to same as previous.
-
Jul 1998
Reroofing.
-
Jun 1998
Comply with nov - repairs to rear stairs.
-
Dec 1995
Replace underground diesel storage tank.
-
Nov 1995
Termite work per markoff structural epst rept #95811.
-
Jul 1991
Install garage door & driveway & depress basement slab.
-
Sep 1990
Reroofing.
-
Mar 1989
Dry rot repair, replace shower surround and subfloor.
-
Jan 1989
Reroofing.
4 nominal $1 street-space permits are omitted.
Not yet documented: the architect and builder and the early residents. Know any of it? Tell us — just describe it in plain words.