1026–1028 Capp Street
Mission · San Francisco, CA 94110
Permit history
-
Jul 2023
Per permit application 202102245270, cancell address 1024 capp st, the new address will be 121 lilac street (new building).
-
Jul 2023
Pe permit application 202102245270, add new address to apn 6528/005 as; 121 lilac street.
-
Jun 2023
Construct new site steps between front and rear portion of property.
-
Feb 2023
New fire sprinkler plan. design of residential fire sprinkler plan and hydraulic calculations. installation of residential fire sprinkler system with cpvc. ref permit 202102245270.
-
Oct 2022
Revision to permit application 202008202258. replace five foot portion of existing concrete foundation at north west corner of the building with new reinforeced concrete foundation.
-
Jul 2022
Installation of a new sprinkler monitoring system. ref 202204202607.
-
Apr 2022
Add fire sprinkler system throughout 3 floor of new adu behind existing building per nfpa 13 d, connect to existing fire sprinkler system oat front building. (total sprinklers 20) ref app#202008202258.
-
Jan 2022
Install minisplit system for bottom unit (1026 a capp).
-
Jan 2022
Per permit application 201911076685 and permit application 202008202258, add address to new adu at apn 6528-005 as; 1026a capp st.
-
Jun 2021
Install new fire sprinkler system throughout ground floor per nfpa 13 including 2" dedicated fire service per nfpa 24 (total sprinklers 19). ref # 2019-0820-2258.
-
Feb 2021
Construction of new accessory dweeling unit (adu) building in the rear (west) of the property.
-
Aug 2020
Revision to 201911076685. separate lower 2 story unit into 2 separate units. install 1 additonal kitchen. remove 1/2 bath at 1st fl and install 2 new baths. reconstruct exterior stair from 3rd and 2nd fl in rear. project is currently in initial stages of construction.
-
Nov 2019
1st floor: incorporate existing workroom & storage space into existing lower unit. 2nd floor: remodel existing bathroom & construct new bathroom; remodel existing kitchen. 3rd floor: remodel existing bathroom & construct new bathroom; remodel existing kitchen. all floors: reconstruct in severely decayed (dry rot)roof.
-
Jan 2009
Reroofing.
-
Oct 1986
Removed 3 existing bathrooms in basement.
1 nominal $1 street-space permit is omitted.