431–435 Capp Street
Mission · San Francisco, CA 94110
Permit history
-
Dec 2022
Demolition existing siding, waterproof exterior with tyvek paper. installation of fiber cement boards. work in common area.
-
May 2019
Sprinkler monitoring fire alarm installation, facp, manual pull, heat detector. aes radio and monitoring modules.
-
Sep 2018
Perform repairs as per termite report # 80929, item # 2a.
-
Dec 2017
Revsion to permit application 201702149410. modify dormers at south side of building.
-
Nov 2017
Fire sprinkler installation on 1st fl and garage. 12 ft underground 2" copper, #17 heads ref 201708306478.
-
Sep 2017
Administration permit for change ddress at unit legalization from 431, 433 capp st to 435 capp st at block 3595, lot 041.
-
Sep 2017
Per permit application 201702149410, add address to leglize unit at ground floor as: 435 capp street at block 3595, lot 041.
-
Aug 2017
Revision to 201702149410 and 201702149399, add 1 bath and 1 bedroom to new gr fl unit. full demolition and replace rear of building at rear structure and rear stair, rebuild in kind stair due to decay.
-
Feb 2017
New roof deck @ rear of building @ 3rd story level. existing roof, adding guardrails @ existing roof to create roof deck-in req'd rear yard set back.
-
Feb 2017
Existing: 2 unit residential building: add 3rd unit at ground floor. no new walls, new kitchen, bathroom, bed room, and living space. sprinklers at ground level under seperate permit. (nfpa 13r).
-
Dec 2016
Revision to permit application 201608306316: remodel one unit at 2nd floor, remodel one unit at 3rd and 4th floor level. modify floor plans at 1st, 2nd, 3rd, & 4th floors. modify structural foundation/framing and add dormers.
-
Oct 2016
Remodel attic only- add a bathroom, legalize playroom and bedroom.
-
Oct 2016
Install 3rd unit on ground floor with bathroom & kitchen.
-
Aug 2016
Temporary shoring of wood structure to accommodate foundation installation. excavation sequence to accommodate foundation replacement. new foundation.
-
Jul 2016
Remodel 2 units, remodel kitchen & bathroom, add bathroom in each unit.
-
Jun 2016
Exterior paint & interior paint, all new flooring, install can lights, new sockets & switches.
-
Oct 2003
Reroofing.
3 nominal $1 street-space permits are omitted.
Not yet documented: the architect and builder and the early residents. Know any of it? Tell us — just describe it in plain words.