25–27 Dolores Terrace
Mission · San Francisco, CA 94110
Permit history
-
Jun 2022
Recommencement and completion of work approved under permit application 201902132828.
-
Feb 2019
Install unoccupied living roof & maintenace rail above garage. not visible from stret.
-
Nov 2018
Add new roof deck in buildable area.
-
Feb 2016
As built fire sprinkler drawings. ref app#201205180774 & 201306139394r-1 n/a for maher.
-
Jan 2015
Install new fire sprinkler system per nfpa 13r throughout the building includes 2" underground fire services total = 56 heads, appn. 201410300308.
-
Nov 2014
Enlarging an open deck with accessibility from the unit below through a roof hatch. revision to permit# 201409126225 & 201410300308.
-
Oct 2014
Revision to permit application 201409126225: infill existing entry on 1st floor & remodel facade - windows & doors, apply new plaster finish.
-
Oct 2014
Install evauation sings on floors: basement, 1st to 4th floor, roof. n/a maher ordinance.
-
Sep 2014
Reduction of existing rear garage form 877 sq to 633 sq, , alteration of exterior stairs in middle yard, structural, new foundation & framing for garage. bath room and kitchen remodel.
-
Aug 2014
Add address to block 3578, lot 052 as; 25, 27 dolores ter.
-
Aug 2014
Additional work to 201205180774; particularly addition of design of staircase #1 (at the north elevation) also staircase #2 (south elevation), pls refer to dwg e.1 & e.2 for staircase locations; maher n/a.
-
Jul 2014
Structural strengthening per plan.install plywood sheathing @ all floors, new center beam and upgrade foundation.
-
Jul 2014
Revision appl. 2012.0518.0774. revision to the general notes of water closet dimension from wall to grab bar and 42"x48" shower to comply with cbc 1134a.6. maher n/a.
-
Jul 2014
Remodel existing 2 kitchens & 2 bathrooms of uppper and lower units of duplex' to comply with cec150(k) 8 & 10.
-
Jun 2014
Reroofing.
-
Nov 2013
Install garage exhaust system, install kitchen and bath exhaust system, install co2 monitor system, install 2 duct for osa. new building permit application 2012/05/18/0744 architectural permit approved. ** maher: compliance with ordinance no# 155-13 not required **.
-
Jun 2013
Install new underground piping and new riser for 4 floors and basement. standpipe system installed.install (106) upright sprinklers/(564) pendent sprinklers/(26) sidewall sprinklers. provide all bracing per nfpa and seismic bracing calcs. provide calc plates on riser. standpipe.
-
Dec 2012
Shoring for excavation at 25 dolores st project. (reference: approved permit #201205180774).
-
May 2012
Erect four story 37 units apartment building.
-
May 2012
To demolish 1 story warehouse building.
-
Jul 2003
Seismic upgrade of umb structure.
-
Jan 2000
Parapet bracing.
-
Jun 1998
Parapet safety program (ref. 9312967).
-
Feb 1997
Otc alterations permit.
-
Sep 1993
Replace rear strs-repair rear porch structural posts & joists.
-
Aug 1993
Parapet safety program.
-
Apr 1990
Replace automotive paint spraybooth in same location.
-
Nov 1989
Ewo-s.
-
Dec 1988
Reroofing.
-
Jul 1983
Additions alterations or repairs.
6 nominal $1 street-space permits are omitted.
Not yet documented: the architect and builder and the early residents. Know any of it? Tell us — just describe it in plain words.