One unit -due to water damage; remove & replace one sheet of plywood in the hallway like for like and install new dry wall.
-
Nov 2024
One unit; install blocks and extra support to existing framing to improve existing stair connection.
-
Mar 2023
Remove 50 sq ft of tile: remove 36sqft of stucco: remove and reinstall existing sliding door: install 50sqft of plidek waterproofing: install 50sqft of tile (due to water damage).
-
Mar 2023
Remove 50 sq ft of deck tile: remove 36sqft of stucco: install 50 sq ft of phidek waterproof: instal stucco in kind-remove and reinstall 1 sliding doors in kind- install new tile 50 sq ft.
-
Sep 2022
One unit: remodel bathroom not changing floor plan.
-
May 2021
Reroofing.
-
Mar 2021
One unit: like for like bathroom remodeling, convert tub to shower u.r.l., 1 exhaust fan, 2 gfi, 2 swith, 2 j box.
-
Jan 2021
Remove exist tile on deck patio, demolition stucco in order to add new deck to wall flashing, recoat membrane, new buidling paper lath at removed and location retile deck patio.
-
Nov 2016
Remove tile, 12" band of stucco and water proofing at deck. remove and reset door with new flashing, install new water proofing, replace tile and stucco in kind to match existing.
-
Jun 2014
#15. remove 8'x8' area to expose wood deck, remove 3'x10' to allow damaged decking. re-install wall 3 flooring in a like for like manner to resemble existing. not to exceed 64 sq ft of sub replacement.
-
Dec 2009
Modification of powder room & raised paltform at 2nd floor, storage at ground floor to document previiously existing work done without permits.
-
Nov 2009
To comply with ces nov # 200914381 dated 7/22/09. build new 1 hr rated wall, a door and hand rail/ guard rail replacement at original location.
-
Sep 2009
Remove stucco around door & window to install new waterproof. remove railing lags & install scalant reinstall lags, remove 1st row of tiles on deck. install new edge metal & saddles. apply new waterproof membrance to tie in with existing. reinstall tile & stucco, not visible from street.
-
Dec 2001
To install fire alarm system/11pull station/1 flow sw 2 tampers 2 heat det.
-
Mar 2001
Fully sprinkler for the building.
-
Nov 2000
Underground connection for fire sprinklers.
-
Aug 1999
Demolish a one story manufacturing/office building.
-
Aug 1999
Erect a four story twenty unit live/work building.
-
Sep 1997
New handicap toilet room and installing new type x gypsum.