2601 Mariposa Street

Mission · San Francisco, CA 94110

  • Built 1989
  • Industrial building
  • 3 stories
  • Zoned PDR1G
  • District 9
  • Historic status: not a historical resource
37.7629, −122.4097 Street View appears here once a Google Maps embed key is configured.
161,125 sq ftBuilding area
52,500 sq ftLot area
  1. Jul 1983

    Demolitions.

    Complete Permit 8307375
  2. May 1985

    New construction.

    Complete Permit 8505499S $$$ $5,800,000
  3. 1989

    Built as a commercial building, recorded as occupied by KQED.

    Showplace Square / Northeast Mission Historic Resource Survey, adopted 2011
  4. Oct 1989

    Sremodel existing building to accommodate t.v & radio studios.

    Complete Permit 8919185S $$$ $7,000,000
  5. Oct 1991

    Vertical addition.

    Complete Permit 9120293 $$$ $100,000
  6. Jun 2001

    Replace existing diesel generator with new. extend existing conc. housekeeping pad to accommodate new generato.

    Complete Permit 200106292736 $$$ $48,000
  7. Dec 2001

    New full ht. non-bearing walls/door/ups equipmt, stru/mechanical/electrical component to support ups.

    Expired Permit 200112135210 $$$ $30,000
  8. Sep 2002

    Oti-1 2nd floor, el, me, ls, sp.

    Expired Permit 200209126335 $$$ $200,000
  9. Sep 2002

    Oti-2 2nd floor, el, me.

    Expired Permit 200209126337 $$$ $100,000
  10. Nov 2002

    Oti-2 2nd floor el me.

    Issued Permit 200211040660 $$$ $275,000
  11. Nov 2002

    Oti-1 2nd floor elme sp.

    Expired Permit 200211040659 $$$ $200,000
  12. Dec 2002

    Structural- acoustic floor & metal stud wall framing.

    Expired Permit 200212203959 $$$ $40,000
  13. Jul 2010

    Furnish & install (1) boiler (like for like) - with five vents & piping; furnish and install (1) pump (like for like); furnish and install 1 thermostatic 3 way valve -(like for like).

    Issued Permit 201007065955 $$$ $100,000
  14. Nov 2012

    Replace existing rooftop air handlers ahu-3 with new packaged rooftop air conditioning unit per plans.

    Complete Permit 201211204587 $$$ $600,000
  15. Jul 2013

    1st floor - adding walls, ceiling joists, & door to create a media arvhile room. electrical, mechanical, sprinklers to be under a separate permit.

    Issued Permit 201307313268 $$$ $45,000
  16. Jan 2014

    Revision to appl #2013.07.31.3268 - move the location of tape library to adjacent area on same floor & add a medchanical lift. #2 compliance with app 115-13 not required.

    Issued Permit 201401085833 $$$ $1
  17. Apr 2014

    Revising existing space for raised floor. server rack room. electrical/mechanical/sprinklers are under a seperate permit.n/a maher.

    Issued Permit 201404032410 $$$ $60,000
  18. Sep 2014

    Replace plumbing fixtures with new. extend plumbing piping to new plumbing fixture locations, provide new supplemental floor heaters near shower locations, reroute existing mechanical. ductwork per plan, one toilet under permit application 201408274903. n/a ordinance #155-13.

    Issued Permit 201409186718 $$$ $80,000
  19. Feb 2015

    Level 2: provide electrical for new racks and equipments for nfew tech center. provide power and lighting for new mezzanine and storage room. ref app#201408274902. n/a for the maher.

    Issued Permit 201502117990 $$$ $330,000
  20. Feb 2015

    Level 2: furnish and install new ducting supply and return new fan coil. new condensing units. ref app# 201408274902. n/a for the maher.

    Issued Permit 201502117987 $$$ $85,000
  21. Jul 2016

    Remove and replacew 1 existing 85 ton packaged hvac unit maher na.

    Complete Permit 201607011457 $$$ $450,000
  22. May 2018

    Furnish & install (2) new vrf split system hvac cooling only units to serve electrical closets. n/a for maher.

    Issued Permit 201805310579 $$$ $175,000
  23. Sep 2018

    Enlarge entry & expand footprint @ nw corner. add mezz at roof level for multipurpose meeting room, catering kitchen, lunch room & roof terrace, renovation of interior spaces, seismic improvements, mep upgrades. maher n/a.

    Complete Permit 201809251300 $$$ $24,000,000
  24. Aug 2019

    Tempotary shoring for structural work coverd under shoring posts and shoring towers installed under existing slabs.**maher n/a**.

    Complete Permit 201908148824 $$$ $110,000
  25. Jun 2020

    Modify existing fa, add (2)remote annunciators, (7)remote power supplies, (6)sync output modules for power supplies, (5)smoke detect, (30)control relays, (12)monitoring modules, (161)ceiling horn/strobes, (26)wall mount horn/strobe, (20)wall mount strobes, (49)ceiling strobes, (1)heat detector, (21) duct.

    Complete Permit 202006188890 $$$ $150,000
  26. Jul 2020

    Added sidewall heads to top of freight elevator shaft, added clarification notes for hazardous storage conditions and codes that design is complying to in the other clarifications section on the right of each sheet.

    Complete Permit 202007190464 $$$ $678,000

DBI holds 105 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 105. 3 of them are nominal $1 street-space or sidewalk permits.

Not yet documented: the architect and builder and the early tenants. Submit an update