Permit history
-
May 1991
Legalize existing kitchen.
-
Apr 2003
Install sprinkler system as per sfo ordiance #170-02. comply nov 199710599 eid.
-
Aug 2006
Install automatic fire sprinklers.
-
Mar 2009
Establish hotel room count, occupancy relocations & site permit for service penthouse; heaters are to be relocated to roof. legalize six additional tourist rooms.
-
Jul 2009
Installation of new fire alarm communicator only to existing fire control panel.
-
Dec 2011
Change of use/conversion of vacant 1268 sq ft comm'l space to a full-service restaurant. incl slight rework of existing storefront to accomodate new accessible entrance, new dining area, bar, kitchen, storage areas & accessible bathroom to be constructed.
-
Sep 2012
Address dbi complaint #201249102 plus subsequent site inspection and corrispondence with housing inspection of dbi. remove 2nd fl. partion wall for access to fire escape. field verify sprinkler and f/a coverage is ok.
-
Dec 2013
2nd and 3rd floor: remodel of shower rooms on both floors, new bathroom at manager apt on 2n fl. remodel of reception area on 2nd fl., new windows at building facade both floors, mep ls and sprinklers on separate permits. jjc.
-
Dec 2013
Mandatory seismic upgrade to existing "soft story" construction. new accessible ramps to be added at entries to the 1st retail spaces. cost of construction - exclude moment frame & its foundation work cost.
-
Feb 2014
Install new fire alarm system throughout connect exisitng water flow & tamper switch (installed by ohers) to new panel, nfpa 72 central sysem monitoring refapp# 201312063567 & 200608220182.
-
Mar 2014
Relocate existing sprinkler to accomodate minor framing changes. add 2, relocate 6.
-
Jun 2014
Revision appl. 201312063565. structural modification. additional foundation at center and south wall in kind.
-
Jul 2014
New laundry room and storage spaces at 1/f, with new exterior ramp to provide disabled access. mep. & sprinklers permitted seperately.
-
Aug 2014
Construct accessible toilet room, install new lighting and electrical.
-
Sep 2014
Due to remodeling on 1st floor, 5 horn/strobes & 3 strobes will be installed & tie-in to existing control unit, permit application 201407171469.
-
Oct 2014
New electrical service, work includes new concrete pad/slab to support new electrical equipment (new pg&e transformer and electrical service board) and new fence and gate at property line along 15th st.
-
Jun 2016
Change of use. tenant improvement project to build out 1st fl space as a restaurant. work to include new walls, doors, millwork, soffits, ramping & finishes. mep, fire sprinklers, life safety & title 24 under separate permit.
-
Aug 2018
To obtain a final inspection for work approved under permit #201410179182. all work is complete.
-
Sep 2018
To finilaze work done under expired permit application 201407171469.
-
Aug 2019
As builts 201509046212 due to remodeling on 1st floor, 6 new notification devices will be installed on 1st floor & tie in to existing control panel.
-
Aug 2021
Underpinning & lagging at north property line of 1906 mission st to facilitate proposed excavation at 1900 mission st. ref permit application 201507080963, 201912189840, 202108257106.
-
Apr 2022
Railing installation as per violation notice #202289651: repair less than 50% (interior only).permit to comply with nov's shall include all items identified for both mentioned above.
-
Aug 2024
To comply with nov # 202424553 remove commercial roll up door & illuminated sign.
-
Mar 2025
Illuminated sign channel letter "fashion alley".