808 Leavenworth Street
Nob Hill · San Francisco, CA 94109
Permit history
-
Jun 1986
To bring building into full compliance as required by dahi.
-
Jan 1989
Parapet reinforcing.
-
Aug 1991
Horizontal addition.
-
Mar 1995
Re-install fire escape ladder, correct stair treads.
-
May 1997
New restroom, lighting in kitchen area.
-
Mar 2007
Remodel 1 kitchen & 1 bathroom patch & paint walls & ceiling under seven units.
-
Jun 2007
Work on#202 & #406. remodel 1 kitchen and 1 bathrooms. patch and paint walls and ceilings for two units.
-
Jun 2007
Remodel of kitchen bathroom patch and paint ceilings and walls upgrade fixtures and appliances (no change to partitions or windows.
-
Jul 2007
Remodel of two units - update electrical to code. move drain and gas line. upgrade appliances and fixtures. patch and dpaint ceilings and walls.
-
Aug 2007
Remodel one unit. demolish kitchen and bath, new appliances and fixtures, upgdate electrical to code. patch and paint ceilings and walls, new tile floor coviering in bath and kitchen. new lighting. flourescent/occupance sensor.
-
Aug 2007
Reroofing.
-
Oct 2007
Work on one unit.remodel of apartments. bathroom lighting to be fluorescant on occupant sensor. demolition of existing cabinets in kitchen, couter tops, bathroom tile and fixtures, upgrade appliances and fixtures, new cabinets and countertops patch and paint walls and ceiling new tile in bathroom 1 bathroom &.
-
Dec 2007
Comply with nov # 200730911. build new handicap counter, add freezer plug in. change of use to small self server restaurant/cafe' relocate atm.
-
Dec 2007
Work @ two units only. remodel apartments. no sturctural. demolition of 2 kitchens & 2 bathrooms. remove 9e) cabinets in kitchen countertops. bathroom tile & fixtures. new cabinets counter tops & tile in kitchen & bathroom. upgrade fixtures & appliances. existing uif light are changed.
-
May 2008
Work @ one unit & one unit only. remodel of 2 kitchens & 2 bathrooms. demolition existing cabinets, counter tops, tile, appliances & fixtures. install new cabinets, countertops, tile fixtures & appliances, patch & paint walls & ceilings.
-
Oct 2008
Three units. kitchen & bathrm remodel. no struc. work, no lighting work. replace bathrm window in the lighwall (same size). replace cabinet, counter, floor and wall tiles and fixtures.
-
Aug 2010
To obtain final inspection for work approved under permit application 200712190851. all work is complete.
-
Aug 2010
To obtain final inspection for work approved under permit application 200708170103. all work is complete.
-
Aug 2010
To obtain final inspection for work approved under permit application 200810154202. all work is complete.
-
Aug 2010
To obtain final inspection for work approved under permit application 200805051353. all work is complete.
-
Aug 2010
To obtain final inspection for work approved under permit application 200703065580. all work is complete. for units: 203, 206, 302, 303, 305, 402, 403.
-
Feb 2011
To obtain final inspection for work approved under permit application 200712190851. all work is complete.
-
Feb 2011
To obtain final inspection for work approved under permit application 200708078997. all work is complete.
-
Feb 2011
To obtain final inspection for work approved under permit application 200703065580. all work is complete.
DBI holds 34 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 34. 5 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early residents. Submit an update