1301–1327 Polk Street
Nob Hill · San Francisco, CA 94109
-
1907
Built at large-apartment scale along the Polk Street corridor but opened as a hotel for temporary guests rather than long-term flats.
-
Mar 1982
Additions alterations or repairs.
-
Nov 1989
Ewo - s.
-
Mar 1990
Provide plans for parapet safety sect to review inspect.
-
Jul 1998
Umb seismic retrofit general procedure.
-
Feb 1999
Interior non-structural demolition only under this permit.
-
Jul 1999
Roof repair and replacement of damaged member for fire dmage.
-
Sep 1999
Repair water damage.
-
Mar 2000
Street space.
-
Jul 2000
Street space.
-
Jul 2000
New fire alarm system.
-
Nov 2000
Sheetrock of all studwalls & ceilings of the commercial spaces. accessible entrance & toilet.
-
Dec 2000
Street space.
-
Jul 2002
Remodel of exist 108 units to 72 units apartment for low-income senior citizens. community spaces.
-
Mar 2003
2 new unisex ada compliance rest rooms new exit stair and exit pathway out of 2 comm'l spaces as 2nd.
-
Mar 2004
Install fire sprinkler in existing building.to comply with sprinkler retrofit ordance 170-02.
-
Aug 2004
Fire sprinkler in the basement.
-
Aug 2004
Add horn/strobe lights, smoke detectors to existingfire alarm system, ada rooms, heat det.
-
Sep 2004
Proposed a new laundromat at existing ground floor.
-
Oct 2004
Revision to permit appln #2002/07/29/2568s sidewalk structural repair.
-
Jun 2005
Building working and a storage area.serving counter, building a hood system.
-
Apr 2007
Install new sidewalks on bush & polk street. install new retaining walls at building basement, backfill udner new sidewalks filling basement under existing sidewalks on bush & polk. demolition existing basement retaining walls under existing sidewalks.
-
Dec 2008
To complete work and obtain final inspection for work approved under permit application 200704199205.
-
Jun 2009
Refer to permit application 2008-1203-7762-relocate & replacing 8 sprinkler heads with quick response pendent sprinklers. this permit is for fire sprinkler only.
-
Nov 2020
1/f: tenant improvement: relocate 2 offices to rear of building, upgrade lounge with new reception desk and ceiling.
-
Nov 2020
Reroofing.
DBI holds 71 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 71. 6 of them are nominal $1 street-space or sidewalk permits.