Permit history

  1. Jun 1984

    Sign - erect.

    Complete Permit 8406067 $$$ $1,000
  2. Jun 1987

    Demolition exist lightwell, closet, install new dumb waiter shaft.

    Expired Permit 8707880 $$$ $51,000
  3. Mar 1988

    Demolition of existing shaft & rooms as needed.

    Complete Permit 8803302 $$$ $53,000
  4. Apr 1988

    To extend expired appli #8707880.

    Complete Permit 8805185 $$$ $30,000
  5. Mar 1989

    Minor modification to meet existing conditions for elevator.

    Complete Permit 8904135 $$$ $5,000
  6. Jan 1990

    Minor modifications for clearance of new elevator motor.

    Complete Permit 9000356 $$$ $2,500
  7. Mar 1990

    Minor modifications for clearance of new elevator motor.

    Complete Permit 9005577 $$$ $2,500
  8. Jun 1990

    Modif. for clearance of elevator doors refer #9005577.

    Complete Permit 9012828 $$$ $1,200
  9. Nov 1990

    Minor modifications to bearing wall to create addit'l space.

    Complete Permit 9023525 $$$ $1,500
  10. Feb 1993

    Install 12'gate across alley at rear/gate attached to corner.

    Expired Permit 9302453 $$$ $3,600
  11. Apr 1993

    Relocate gate per #9302453.

    Complete Permit 9306125 $$$ $470
  12. Jan 1994

    Replace existing hand rails, post & ballustrades with new.

    Complete Permit 9401395 $$$ $4,500
  13. Aug 2002

    Seismic strengthening as setforth in degenkolb engineers drawings dtd 7-15-2002.

    Expired Permit 200208224688 $$$ $350,000
  14. Jul 2007

    Permit to supplement/complete permit 1060735, permit application 2002/08/22/4688. seismic strengthening (2nd phase) as set forth in cornerstone structure engineering group plans - pages / sheets 50.0, 51.0, 51.1, 51.2, 52.0, 52.1, 54.0, 55.0 date july 2007." special procedure / bolts ".

    Issued Permit 200707197272 $$$ $350,000
  15. May 2010

    To complete work and obtain final inspection for work approved under permit application 200707197272.

    Issued Permit 201005031587 $$$ $6,000
  16. Sep 2011

    Fire alarm system replacement, phase 1 of approved c.a.p. this includes a new facp, ann, 1bps, 22 smoke detectors, 5 heat detectors, 1 pull station, 3 door holders and 13 nac devices.

    Complete Permit 201109074036 $$$ $14,740
  17. May 2013

    To obtain final inspection for work approved under permit application 200208224688. all work is complete - seismic improvemnet work.

    Complete Permit 201305015895 $$$ $1
  18. May 2013

    To obtain final inspection for work approved under permit application 200707197272. all work is complete - seismic improvemnet work.

    Complete Permit 201305015897 $$$ $1
  19. Jun 2013

    Renew for final 201109074036 phase 1 fire alarm.

    Complete Permit 201306058745 $$$ $1
  20. Jan 2014

    Construct lobby level & stairway (all) ada accessibility improvements includes accessible entry, guest service counters, stairway handrails, public restrooms & ada signs.

    Cancelled Permit 201401277089 $$$ $140,000
  21. Aug 2016

    Voluntary fire alarm upgrade to preview permit #2013-06-05-8745. phase ii plan of action: common areas, corridors, electrical, phone & mechanical room. voluntary upgrade of initiating: notification applicances.

    Complete Permit 201608155023 $$$ $10,000
  22. Sep 2018

    To obtain final inspection for work approved under permit application 201608155023. all work is complete.

    Issued Permit 201809059155 $$$ $1

1 nominal $1 street-space or sidewalk permit is omitted from the timeline.