Otis Elevator Company Building
1 Beach Street
-
1924
The Otis Elevator Company's western assembly plant was built over 1923 and 1924 on a lot 275 by 137.5 feet, designed by the company's own architectural office in Yonkers. It went up as two storeys, the lower one tall enough to take railway wagons, with combed brick and tan terra cotta on the street fronts, eighteen bays along Beach Street and nine along Grant Avenue, each bay carrying one tall round-headed arched window under a Lombard band of six small arches. A railway spur ran in through the Grant Avenue side.
-
1924
The plant assembled lifts and made the selector mechanism for the company's Signal Control System, and served the whole United States west coast plus Nevada, Arizona, Alaska and Hawaii, with smaller buildings of similar design in Los Angeles and Portland.
-
1939
With new construction at a standstill through the Depression, the plant was turned over entirely to servicing and maintaining lifts rather than building them.
-
1970
The lift company left in 1969 and the building became offices for a health insurer. A middle floor was inserted into the tall ground storey, making three floors of two; the internal railway track and sliding crane came out; the lower window sash was replaced with a black metal storefront system and the end-bay windows enlarged to match the rest; and the two Beach Street entrances were closed up in favour of a new recessed entrance in the eighth and ninth bays.
-
November 5, 1970
The Otis Elevator Building in the Northern Waterfront area had recently been renovated and leased to a single tenant employing 600 to 700 people.
-
1971
Built.
-
Nov 1990
Seismic repair.
-
1998
The interior was stripped back for multimedia tenants: the concrete piers exposed, the dropped ceilings taken out with the piping and wiring left showing, and the inserted middle floor removed in two places to restore rooms of the original double height under the skylights.
-
Feb 1998
Mm2 el-me-ssp - 2nd floor.
-
Feb 1998
Mm2 el-me-sp 1st floor.
-
May 1998
Mm1 3rd floor el/me.
-
October 21, 1999
Listed on the National Register of Historic Places, significant for the part its lifts played in the building boom that changed the San Francisco skyline in the late 1920s, and for the assembly and control manufacture carried on here.
-
Sep 2002
Oti-1 3rd floor, el, me, ls, sp.
-
Nov 2002
Oti-1 3/f el me ls sp.
-
Mar 2004
Interior ti incl drywall, electrical, mechanical&plum.interior finishes.
-
Feb 2012
Tenant improvement; change offices into classrooms; remodel existing classrooms into offices. including associated change of use. life safety separate.
-
Feb 2013
1st & 3rd floor restroom remodel - new fixtures, finishes & restroom partitions, new finishes at common area.
-
Sep 2019
Remodel of interior ground floor entrance lobby to 2 floor hgh space & addition of new roof deck. extension of elevator stop to roof & extension of stair to roof. seismic upgrade. ** maher: n/a **.
-
Nov 2020
Interior demolition of non-structural partitions, ceilings and finishes on levels 01, 02 and 03. no exterior work per ab-017. no change of use under this permit.
-
Nov 2020
Replacement of 1st floor slab on grad with reinforce concrete structural slab. interior structural work only all other work under permit application 2019-0923-2380.
-
Dec 2020
Interior core & shell improvements. remodel grnd floor main lobby, new cut-out. infill of 2nd floor openings. cosmetic upgrade of existing egress stairs, new restrooms on level 01-03. no change of use; no new office use.
-
Aug 2025
G/f t.i. non-structural partitions, ceilings, restrooms, showers & lighting, new parking. office allocation & parking per 2022-009996 cua & 2022-009996 ofa. gym not for public use.
-
Sep 2025
1&2/fl- ste 200/100- ti non structural partitions, ceilings, fixtues, doors, finishes. mep deferred. no change of planning use from institutional to office under this permit.
-
Sep 2025
2/fl- ste 250- ti non structural partitions, ceilings, fixtues, doors, finishes. mep deferred.
-
Nov 2025
Suite 300 tenant improvement. non-structural partitions, ceilings, fixtures, doors and finishes. mep deferred.
-
Jan 2026
Level 1 and level 2: suites 100 and 200. deferred mep for 202509084794.
-
Jan 2026
2nd fl, ste 250 deferred mep for permit application 202509084793.
-
Jan 2026
Ste 300 - deferred mep to 202511240285.
-
Mar 2026
3rd/f ste# 350: office t.i. included non-structural partitions, millworks & finishes, modification of stairs e) enclosure on adding 2 roll down fire shutters, mep deferred.
-
Mar 2026
Ground floor: deferred mep to permit application 202508294258.
-
Aug 2026
1/f suite 150. including non bearing partitions, ceilings, light fixtures, doors and side lites and new finishes. mep deferred.
DBI holds 153 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 153. 5 of them are nominal $1 street-space or sidewalk permits. 2 expired permits are not shown. The assessor's roll gives 1971, the year after the building was converted from a factory to offices; the nomination dates its construction to 1923–1924.