1959
Built.
-
December 1959
Photographed, showing the San Francisco Federal Savings Bank.
-
Nov 1981
Additions alterations or repairs.
-
Oct 1985
Install canopy on the ground floor and roof level.
-
Feb 1986
Renovation of existing bank and installation of canopy.
-
Aug 1992
Enlarge vault.
-
Sep 2002
Repair work due to water damage, new non-load bearing walls at existing location, new ceiling and 6 light.
-
Sep 2003
Install atm to ext wall, enlarge exist atm room.
-
Oct 2003
Furnish and install (1) new fire alarm cocntrol panel, (2) new addressable monitor modules.
-
Jun 2009
Erect a electric wall double faced direct new sign.
-
Aug 2009
Interior demolition to comply with ab 017 on 4th and 6th floors. demolition of select partitions, ceilings, finishes and light fixtures.
-
Aug 2009
Remodel to existing bank basement, 1st fl and 2nd fl. this includes demolition of finishes, non struc wall partitions and case work. new finishes, millwork and non struc walls. minor electrical. work only. two atms replacement of surrounds.
-
Sep 2009
Disabled access upgrades to elevator cab operating pannel. new disabled access restrooms on floors 3-6. new handrails & guardrails. new electrical & plumbing systems. fire alarm and sprinkler under separate permit.
-
Sep 2009
Update the existing fire alarm system. move panel from front entrance to b sement. add annuciator at front door. add smoke detectors throughout. add notification per code. add modules for hp & fsd shotdown throughout building.
-
Oct 2009
Reivsion to 200909015999 to retain existing duct and shaft and replace ceilings on floors 3 and 5.
-
Oct 2009
Replace existing aluminum storefront with new aluminum store front with insulated glazing. new power door operator and new exterior soffit and lighting at existing canopy.
-
Nov 2009
Reglaze of existing 1957 steel and wire glass ( 45 min) rated windows on all six floors except basement. alley windows.
-
Feb 2010
1st-floor-remove existing shaft behind teller to create workable space for ada counter 2nd floor-install motorized interior blinds.
-
Jun 2012
1st/2nd/3rd/4th floors-minor interior work in basement, 1st, 2nd, and 3rd fl including new finishes, new private offices, new equipment. mechanical electrical, fire sprinkler included. deferred submittal: fire alarm.
-
Aug 2013
6th floor-accessibilty upgrades including signage and door actuators required by 6th floor t. i.
-
Sep 2013
T.i.- construct drywall partitions as shown, install new ceiling and lights, mechanical & title 24 under seperate permits.
-
Feb 2018
Remove & replace lighting throughout. t-24. electrical plans only. 1st fl - basement lighting replace.
-
Sep 2020
3rd floor: ti work includes non-structural partitions, associated mep, fixtures, finishes, & casework. upgrades to restrooms.
-
Jan 2021
Modification to storefront & vestibule to remove barrier.
-
Oct 2022
Fa communicator trouble. replace 39 existing smoke detectors with new. replace 11 pull stations with new. replace 1 dual input mod for new sprinkler monitoring. replace 1 mod for new sprinkler monitoring. add 1 fa doc box.
-
Feb 2024
Fire alarm system replacement & add cell communicator. replace 1 facu with new, add 1 cll communicator, add 1 monitor module for communicator; replace 40 existing smoke detector wnew; add 2 heat detector in machine room, replace 14 existing pull stations, 3 monitoring points for wf/tamper, 6 control.
DBI holds 39 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 39. 4 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 1024–1026 Grant Avenue Same street
- 1044–1046 Grant Avenue Same street
- 20–28 Beckett Street Same block
- 4–12 Beckett Street Same block
- 650–654 Jackson Street Same block
- 660–666 Jackson Street Same block
- 706–714 Jackson Street Around the corner
- 716–722 Jackson Street Around the corner