37.8005, −122.4023 A locator map appears here once a Mapbox token is configured.
Know This Place

District 3 · Block 0112, Lot 008 · ZIP 94111

Sperry Flour Company Building

150 Green Street · North Beach

  • 2 stories
  • 29,772 ft2
  • 11,700 ft2 lot area
  • 9 residential units
  • 14 rooms
  • 8 bathrooms
  • Zoned C2
  • Historic resource
  • Sold October 4, 2023
Land$6,823,800
Improvements$4,549,200
Total assessed$11,373,000
37.8005, −122.4023 Street View appears here once a Google Maps embed key is configured.
  1. 1916

    A two-storey reinforced concrete building was put up for the Sperry Flour Company, first used as a private garage and reception room. It is an early example of reinforced concrete construction.

    San Francisco Department of City Planning, 150 Green Street: Draft Environmental Impact Report, Case No. 83.447E, 1985.
  2. 1919

    Assessor’s “built” date.

  3. Apr 2000
    Permit 200004227965 $$$ $250,000

    Renovation of shell & core seismic upgrade new toilet rms on g/f & 1/f new exit stairs new entry wi.

  4. May 2000
    Permit 200005109543 $$$ $30,500

    Installation of new fire service; completely sprinkle lower two floors.

  5. Sep 2000
    Permit 200009200998 $$$ $100,000

    T/i new partitions warming pantry & office spaces mechanical plumb fire alarm & sprinkler under sep permit.

  6. Feb 2002
    Permit 200202118943 $$$ $6,800

    Install structural steel per structural drawings. oti separate permit.

  7. Feb 2002
    Permit 200202149281 $$$ $200,000

    Oti-1, 1st floor, li, me, life safety, sprinkler.

  8. Feb 2002
    Permit 200202280265 $$$ $45,000

    Oti-2 grd floor, ltg, mechanical.

  9. Dec 2004
    Permit 200412070810 $$$ $150,000

    Convert office to recording studio on 1st floor.

  10. Dec 2004
    Permit 200412070807 $$$ $100,000

    Oti-2, 1st floor, el, me.

  11. Mar 2005
    Permit 200503258400 $$$ $26,000

    Demolition of partitions, doors & frames, lights, ceiling tile & grib.safe off mechanical & electrical.

  12. Aug 2005
    Issued Permit 200508019040 $$$ $25,900

    Reroofing.

  13. Jul 2013
    Permit 201307010918 $$$ $50,000

    Install new stair case to 2nd fl mezzanine and open up mezzanine to existing 2nd floor. divide existing partition walls to convert enclosed mezzanine office to open office space.

  14. Oct 2014
    Permit 201410209403 $$$ $42,950

    Reroofing, compliance with maher ordinance no. 155-13 not required.

  15. Jun 2015
    Permit 201506229500 $$$ $47,300

    Reroofing; n/a maher ord. # 155-13.

  16. Jul 2016
    Permit 201607293725 $$$ $400,000

    Demolition of non structural partitions acoustical ceiling grid and tiles & finishes. providing new non structural partitions, new ceiling and finishes maher na.

  17. Oct 2017
    Permit 201710110905 $$$ $150,000

    1/f: office t.i. & single occupant toilket room: demolition of non-structural, act, lighting & finishes, maher n/a. mep under separate permit.

  18. Oct 2017
    Permit 201710302548 $$$ $150,000

    Mechanical including demolition, electrical and plumbing maher not req.

  19. Jan 2019
    Permit 201901150460 $$$ $50,000

    Penthouse b: barrier removal, new ada restroom, and new kitchenette. n/a for maher.

  20. Dec 2023
    Permit 202312273177 $$$ $185,000

    Tenant interior new mens/womens's restrooms and new offices at 1st fl.

  21. Feb 2024
    Permit 202402085564 $$$ $138,500

    2/f tenant interior - new non bearing partitons, new office and office bathroom.

  22. Aug 2024
    Permit 202408017699 $$$ $49,730

    Voluntary installation of a new fire alarm system.

DBI holds 62 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 62. 4 of them are nominal $1 street-space or sidewalk permits. 4 expired permits are not shown. A 1985 environmental review dates this building 1916; the assessor's roll gives 1919.