2055 Sacramento Street
Pacific Heights · San Francisco, CA 94109
Permit history
-
Jan 1981
Additions alterations or repairs.
-
Nov 1982
Additions alterations or repairs.
-
May 1986
Clean building. exterior, install awning/stoneface grill work.
-
Feb 1996
Install a fire sprinkler in existingtrash chute every other fl.
-
Feb 1999
Reroofing.
-
May 2000
Repair fire damage, kitchen to be utted, all cabients & appliance replaced.
-
May 2000
Repair fire damage in kitchen.
-
Jul 2011
One unit; small kitchen remodeling; replace 6-cabinets, 16sq.ft. counter replacement, faucet, install exhaust hood.
-
Oct 2014
Removel of dryall, flooring, baseboards, cabinets demolition permit. complaint # 201499112 & # 201498151. water damage to all units; maher n/a.
-
Oct 2014
Reroofing; compliance with maher ordinance 155-13 not reqiured.
-
Oct 2014
2 to 10/f -remove and replace water damaged drywalls; remove and reset kitchen cabinets; insulation.
-
Feb 2015
Revision to permit application 2014-1022-9642. revise cost of job from 80, 000 to 425, 388.01. replace water damage in-kind to all units per orig app. n/a for maher.
-
Apr 2016
Barrier removal only -new exterior accessible concrete ramp with accessible handrail on both sides of new ramp, n/a for maher.
-
Mar 2017
Two units: remove and replace four aluminum windows to match existing original sliding windows - replace with thermally broken glass glazed with low-e solarban 70 insulated. visible to street.
-
Jun 2021
One for one replacement of existing broken fire alarm system cell dialer added for communication. building to be updated to code compliance in separate permit.
-
Mar 2023
One unit: replace south facing windows for 3 apts in-kind. glazing approx 123.37sf in each apt. to comply with nov202296291.
-
Jul 2023
Eight units: replace south facing windows at 8 units (not facing street), glazing approx. 123.37 sq ft each unit.
-
Nov 2023
Low frequency notification upgrade. install new power supplies. install new notification devices in each dwelling unit to meet the requirement of 75db at the pillow.
-
Aug 2024
Ref 202311301712- as built fa drawings to revis junction box locations and add (8) nac devices.
-
Mar 2025
To obtain final inspection for work approved under permit application 201703222061. all work is complete.
-
Apr 2026
Rebuild the bathroom, no electrical or plumbing work. mold remidation and replace dry wall.
-
Jun 2026
One unit: renovation of 1 apt on 10th level. new kitchen cabinets and new plumbing fixtures. new dishwasher and new washer/dryer. new lighting existing j boxes. no changes to mechanical. no exterior work, fire alarm, or sprinkler work. no structural work.
-
Aug 2026
To comply with nov 202648960 items 2, 4, 6, 8, 12: repair damaged walls and paint; repair the overhead leaks; repair or replace the air handling fan in the lowest level of the garage; repair damaged walls and paint (1001k, d & 1001b13, d, i sfhc); remove cord wiring 1001d, e sfhc, 400.8 nec.
3 nominal $1 street-space or sidewalk permits are omitted from the timeline.
Not yet documented: the developer, the early residents and the date of the last recorded sale. Submit an update