Jul 1989
Horizotnal addition (enclose with patio enclosure wall system).
-
Jun 1991
Brace parapet.
-
Aug 1991
Reroofing.
-
Sep 1995
Add fire control panel complete fire alarm system.
-
Mar 2002
Nov 20122142. upgrade existing ramps, replace existing doors.
-
Dec 2009
Existing panel shall be replaced with a new panel-2 smoke detectors shall be added to the existing system. 2 control relays shall be added to the existing system.
-
Jan 2015
Demolition of non-bearing interior walls cap off existing plumbing @ mains.
-
Jan 2015
Remodel of toilet/shower rooms on the 1st fl level.
-
Apr 2018
Construct room to enclose boiler room. separate permit for plumbing electrical, & exhaust. abatement of pipe insulation by others.
-
Jul 2018
Remodel of existing bathrooms on first and 2nd floors. install new shower valves, sinks, toilets, shower pans, tiles, led electrical lighting with sesonr switch. install a.
-
Aug 2018
Install venting for commercial boiler room and confirm combustion air requirements. ref app#201804257402.
-
Sep 2018
Modifications to an existing gamewell/fci 3r fa system. monitoring of new duct detector in boiler room. no ther work in scope. ref pa.
-
Sep 2018
Modification to an existing gamewell/fci e3 fa system. adding and relocating of visual notification devices in thenewly remodeled bathroom on the second floor.
-
Oct 2018
Revision to permit application 201807235272. t.i of toilet, shower facilities at 1st & 2nd floor south wing drawings to show location of walls and plumbing layout locations.
-
Jan 2019
Address complaint #201768834 to provide interior walls at 2nd floor to allow venting pipes from ground floor to ventilate through roof. to comply with nov #201899231 along with bpa 201810294366. provide 4 ada restrooms.
-
Aug 2020
To obtain final inspection for work approved under permit applications #201809140193 and #201809200890; all work in complete.
-
Aug 2020
To obtain final inspection for work approved under permit applications #200912012331 and #201509194667; all work is complete.
-
Sep 2020
Adding and relocation of visual notificaiton devices in the newly remodled bathroom on the second floor.
-
Sep 2020
To obtain final inspection for work approved under permit application #201804257402; all work is complete.
-
May 2025
Add missing fire sprinkler coverage on main floor and basement.
-
Jul 2025
As built to original approved plans ref permit application 202505015576.
-
Jul 2025
Add (1) monitor module for sprinkler waterflow switch.
-
Nov 2025
All work is at 1/f -project is limited to modifications to the north stair egress path & associated modifications to existing components along this path. scope includes slective demolition of non-load bearing partitions, new rated doors and frames, exit lighting, new exterior exit stair & associated.
-
Dec 2025
Ref ti 202507301926- new door holders shall be provided/120v power for door holder provided by others/ add new relay, 2 notification applicances, 6 addressable smoke sensors.
DBI holds 35 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 35.
Not yet documented: the developer and the early tenants. Submit an update