37.7642, −122.4017 A locator map appears here once a Mapbox token is configured.

444 De Haro Street

Potrero Hill · San Francisco, CA 94107

  • Built 1927
  • Office building
  • 3 stories
  • Zoned M1
  • District 10
  • Historic status: historic resource
37.7642, −122.4017 Street View appears here once a Google Maps embed key is configured.
176,000 sq ftBuilding area
80,000 sq ftLot area
17Rooms · 8 baths
  1. 1927

    Built as an industrial building, concrete construction, recorded as occupied by Western Can Co. Designed by Leland S. Rosener.

    Showplace Square / Northeast Mission Historic Resource Survey, adopted 2011
  2. Feb 1984

    Repair spauling concrete from underside of concrete fl.

    Complete Permit 8401947 $$$ $8,000
  3. Jul 1984

    Remodel lobby, fire corridor, restrooms, elavators, roof etc.

    Complete Permit 8407166S $$$ $5,000,000
  4. Sep 1990

    Const. mezzanine in existing space partition existing space.

    Cancelled Permit 9018471 $$$ $438,000
  5. Jan 2013

    Suite # 208: t.i. commercial for a new office and video production. suite is on 2nd floor with mezzanine. no scope of work to building envelope. mechanical, electrical, and sprinklers under seperate applications.

    Complete Permit 201301168069 $$$ $700,000
  6. Feb 2013

    Interior renovation of restrooms, common corridor and lobby finishes. fire alarm, electrical, plumbing under separate permit.

    Complete Permit 201302089831 $$$ $375,000
  7. Feb 2013

    New entrance doors, new awning & removal of side doors.

    Issued Permit 201302119907 $$$ $165,000
  8. Sep 2013

    Replace existing ground floor property line windows along sidewalk with steel sash to match existing on 2/f.

    Complete Permit 201309056024 $$$ $610,000
  9. Oct 2013

    Construction of a mezzanine on 2nd floor on southside of bldng. to existing walls per plan.

    Issued Permit 201310078695 $$$ $180,000
  10. Jun 2014

    G/f only- no work on 2/f -interior t.i. including minor demolition, new walls, and doors. sprinkler and fire alarm under seperate permit. n/a for the maher ordinance #155-13.

    Complete Permit 201406259465 $$$ $1,400,000
  11. Jun 2014

    2nd fl - tenant improvements to existing office suite on 2nd fl. construction of new mezzanine with stairs & ramp. open offices & support spaces. new lighting & electrical power/data. new mechanical systems incl radiant fl. new plumbing for added restrms & showers. n/a for maher ordinance.

    Complete Permit 201406269566 $$$ $3,384,842
  12. Jul 2014

    1st floor: t.i. to construct new non-load bearing partitions, doors, millwork finishes, electrical/plumbing. fire sprinklers, fire alarm and structural details under seperate permit. n/a for the maher ordinance #155-13.

    Complete Permit 201407292395 $$$ $2,500,000
  13. Sep 2014

    Mechanical and electrical work for tenant improvement 201407292395. install new equipment including exhaust/return, fan coil units. fire smoke dampers, associated plumbing work. exterior louver and roof work on a separate permit.

    Issued Permit 201409116107 $$$ $850,000
  14. Mar 2015

    Reroofing.

    Complete Permit 201503120615 $$$ $341,000
  15. Nov 2015

    Site plan: increase mezzanine area to form new 2/f, add windows to match existing. lower g/f elevation 12".

    Cancelled Permit 201511233336 $$$ $1,000,000
  16. Oct 2017

    Replace boiler & circulating pump with (2) new high efficiency condensing boilers. maher na.

    Complete Permit 201710060584 $$$ $201,437
  17. Jul 2018

    #200: commercial ti in existing 2nd floor suite of existing office building. demolition work include demolition of non-structural interior partitions, plumbing fixtures and lights. new non-structural partitions, plumbing fixtures & lighting to be installed. no exterior work, no work visible from st.

    Complete Permit 201807114281 $$$ $500,000
  18. Aug 2018

    Electrical new power, new lighting and controls.

    Complete Permit 201808227991 $$$ $200,000
  19. Oct 2018

    T.i. improvement- minor demolition, new walls and doors.

    Complete Permit 201810032078 $$$ $200,000
  20. Jan 2019

    2nd floor: t.i. to include new restrooms. mep, fire, & lifesafty under seperate permit. n/a for maher.

    Issued Permit 201901230966 $$$ $45,000
  21. Sep 2020

    Suite 100. interior t.i. open office conference rooms, break areas and storage room. mep deferred.

    Complete Permit 202009154218 $$$ $1,200,000
  22. Sep 2020

    Suite #100: new communicating stair. deferred submittal. ref. permit application 2020-0915-4218 and #2020-1022-7121.

    Complete Permit 202009244944 $$$ $190,000
  23. Oct 2020

    Suite 200: interior tenant improvement: reception conference rooms, break areas & storage rooms.

    Complete Permit 202010227121 $$$ $421,000
  24. May 2024

    Installation and relocation of 12 phone booths and relocate 4.

    Issued Permit 202405071536 $$$ $100,000
  25. Dec 2025

    1/f - interior t.i. for latering kitchen and sq ft dah food service review.

    Complete Permit 202512242618 $$$ $235,000
  26. Jun 2026

    Ground floor- install new 2 hour rated stair access from floor 2 to street level at existing} loading dock. new structrual pad for existing compactor. new lighting and finishes. upgrade existing floor 2 restroom for accessibilityu compliance. mep under seperate permit.

    Issued Permit 202606082742 $$$ $460,000

DBI holds 248 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 248. 6 of them are nominal $1 street-space or sidewalk permits.

Not yet documented: the developer and the early tenants. Submit an update