Jul 1986
Removal of some non-bearing partitions.
-
Jul 1986
Removal of some non-bearing partitions.
-
Aug 1986
Hvac work as per plans.
-
Nov 1986
Erect sign.
-
Nov 1986
Non-structural sign.
-
Mar 1995
Demolition nonstructural partitions/garage floor.
-
Apr 1995
Renovation all 3 floors/retain toilets/stairs/minor ext improv.
-
Oct 1999
Reroofing.
-
Oct 2011
Reroofing.
-
Sep 2017
Demolish existing interior, non bearing walls, doors, side lites, lightsdropped ceiling, remove carpet. no new work, all demolition per ab17, no exterior demolition work, space to remain vacant. n/a ordinance #155-13.
-
Nov 2017
1st floor ti only - new walls, flooring, ceiling, 2 new showers, 2 unisex bathrooms, add bike rack. replace garage doors. add 1 pedestrain door mep under sep permit maher na.
-
Nov 2017
Ti buildout existing space on 3rd fl, no new sq footagel. no change of use, new flooring, new non structural walls, mep under sep permit. maher na.
-
Dec 2017
2nd floor: t. i. build out of existing space on the 2nd floor. no new square footage. no change of use. new flooring, walls. mep under seperate permit. n/a for maher.
-
Mar 2018
1st fl - mechanical plan check for pa 2017-1127-4808 1st floor; n/a maher.
-
Mar 2018
Mechanical plan check for pa 2017-1211-6139 2nd floor; n/a maher.
-
Mar 2018
Mechanical plan check for pa 2017-1127-4825 3rd floor. n/a maher.
-
Mar 2018
Revision to 201711274808 1st fl. remove shower, reconfigure interior corridor, add new slab in garage to level floor, add landing and ramp. interior work only. na maher.
-
Apr 2018
Install new fire alarm system with control panel, smoke above, pull stations, radio comm. throu out in vacant building. ref app#201711274808, 201712116139 &, 201711274825. n/a for maher.
-
Apr 2018
(change of use for 1st floor) convert garage & storage area to office space for bld tenant **maher n/a**.
-
May 2018
3rd fl - revision to pa 2017-1127-4825 add storage closet, remove built in table kitchen, turn conference room into an office, and call out chase per field inspection.
-
May 2018
1st fl - add 2 hour wall in garage with 90 minute door and add new door from stair 2.
-
May 2018
1/f: ti build out of existing space on the 1st fl. only add new lights/lighting title 24 controls.
-
May 2018
2/f: ti build out of existing space on the 2nd floor only, add new lights/lighting title 24 controls.
-
May 2018
3/f: t.i. build out of existing space on the 3rd fl. only add new lights/lighting title 24 controls.
DBI holds 29 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 29.
Not yet documented: the developer and the early tenants. Submit an update