2001–2155 37th Avenue
Sunset Parkside · San Francisco, CA 94116
-
1969
Built.
-
1969
St. Ignatius College Preparatory School, built 1969.
-
Sep 1986
Modify hoods from water wash system to exhaust system.
-
Dec 1990
Raised tennis courts over parking.
-
Apr 1991
Horizontal addition.
-
Apr 1992
Horizontal & vertical addition.
-
Mar 1993
Renovate science lab & corridors on 3rd floor, academic wing.
-
Aug 1995
Remove & replace roof surface & mechanical equip only.
-
Feb 2002
Relocate offices and work room/rearr workroom and storage/replace ceilings/replace heating & air cond.
-
Mar 2002
Track & field site improvement (replace/underground/sidewalk/football field & track surface upgrade).
-
Nov 2005
Horizontal addition to construct a new three level structure. the building will be located in northeast corner of athletic field area. replacing existing outdoor batting cages. the building will include cheral room, classroom, batting cages, storage, weight room, snack bar, patio deck.
-
Aug 2006
Istall new enetry canoppy over existinisg exterior courtyard., structurde & mep are under separate permit. sprikler suytem under separate permit.
-
Mar 2008
Remodel existing kitchen, relocate chef's office & toilet rooms for staff. fire sprinkler & fire alarm under separate permit.
-
Jun 2008
New roof canopy over existing courtyard.
-
Apr 2011
Replacement of existing exterior aluminum bleachers & provide accessible seating.
-
May 2011
Replace existing press box with new press box at athletic field.
-
Jun 2011
1)replace 2 existing pool units in mechanical room and corresponding air cooled condensing units, 2) install new ductwork and drum louvers.
-
Apr 2014
Seismic retrofit to existing buildings.
-
Apr 2014
Replacement of existing exterior doors.
-
Dec 2018
Install electric vehicle charging stations (16) and ada striping. 14 standard stalls 2 ada stalls.
-
Nov 2020
Installation of (4) sport field lighting poles and fixtures including associative electrical infrastructure and additional improvements at st. ignatius football field.
-
Nov 2021
Verizon: new telecommunications facility to be install on existing stadium light including 9 total antennas, 6 rru's, 4 surge suppressors, and other supporting equipment. this pa is submitted with a sow appreal under 2018-012648apl.
-
Jul 2023
Approx 58, 000gsf of demolition of existing educational, kitchen, & accessory assembly spaces. addition of braced steel frame with composite steel & concrete floors. proposed use include educational & accessory assembly on all levels; full kitchen in basement; occupied roof terrace on lev3. new mep system.
-
Sep 2023
Interior ti to the existing snack shack including new walls, metal wall panels, rubber flooring, epoxy flooring, with self coving base & operable corrugated metal doors, snack-shack includes grab & go area & point of service check out locations.
-
Feb 2026
Reroofing: prime substrate with vapor barrier - build up roof with 1" fesco insulation - not mopped down to concrete-substrate. install 1" iso 1/2" densdeck - adherred to concrete substrat adher 72 mil pvc roofing to decks jen, no hot work. crrc#0674-0002a. sri 91.
-
Feb 2026
Reroofing. no hotworks.
-
May 2026
This restroom remodel project involves modification of 5 existing restrooms to include selective demolition and construction of restroom fixtures, accessories, toilet and unrinal partitions, counter tops, lighting and fixtures.
DBI holds 121 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 121. 6 of them are nominal $1 street-space or sidewalk permits.