156–166 Eddy Street
Tenderloin · San Francisco, CA 94102
Permit history
-
Jan 1983
Repair roofing, etc.
-
Feb 1983
Parapet reinforcing.
-
Feb 1985
Stair & iron gate at rear of building.
-
Aug 1990
Non substantial alterations to residential & g/f uses.
-
Jul 1992
Alterations to existing ground fl. new fire rated corridor.
-
Oct 1992
Alt to existing g/f comm'l space n/fire rated corridor restrm.
-
Jan 1993
Replace one paltform on firescape & connecting ladder of 2nd.
-
Feb 1993
Install 8'high partit.walls with 25 gauge steel studs/24"on cen.
-
Aug 1993
Sidewlk reconstr-160 eddy st-watweproof sidewalk.
-
Mar 1994
Install new canvas awning over building store front entrance.
-
Jun 1994
Renewal of permit inspection permit application 9313966.
-
Jul 1999
T.i. improvement at the grnd floor for vietmanese youth dvlpnt.
-
Jun 2004
To comply with nov 200341186- install 3 sprinkler heads at storage rm, one each at 1st floor, 3rd floor usi.
-
Mar 2008
Replace 2500 square feet 5/8 type "x" drywall in basement. repair drywall in rooms #423, #323, #223 from water damage. reinstall 100 lf of surface mounted conduit in basement. remove & reinstall 3 plug & 3 smoke dect. remove & reinstall 3 sink. due to water damage.
-
Mar 2010
Minor alterations to ground floor commercial space. partitions & doors, including minor alteration of 1 hour corridor. installation of automatic door opener on entry door. field verify if sprinkler/life safety is required under seperate permit.
-
Jun 2010
Install new ductwork per sheet m-2 to provide air to stage and dressing room.
-
Nov 2012
Install new hvac system at basement.
-
Oct 2015
Add attic insulation to existing. r-40 equivalent.
-
May 2019
Rewire unit/room 228 and install 5/8" type x sheetrock at walls and ceiling and insulation at ceiling. r-19 min. install toilet and vanity sink. no change to existing layout. install underlayment for ltp floor.
-
Jan 2024
Renovation of storefront for accessible entrance and renovation of entry area.
-
Jan 2024
Reroofing.
-
Mar 2024
Remodel all communal bathrooms on 2nd, 3rd, and 4th floors (note guess rooms will not be removed).
-
Apr 2024
Replacement of fire alarm panel.
-
Aug 2025
Community shower room repairs, 12 shower rooms. on 2nd, 3rd and 4th -all accessible features to be remained.
DBI holds 36 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 36. 2 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update