706–710 Ellis Street
Hotel
-
1907
Built as the Marathon Apartments, apartment building with six 4- and 5-room units on each floor, to the design of the architects Crim and Scott. Four storeys over a basement, brick structure, two-part vertical composition, Renaissance/Baroque ornamentation.
-
1908
Built.
-
March 11, 1908
Thomas H. Day's Sons, J. Looney and J. E. Steere contracted to put up a four-storey and basement brick building for the Moffatt estate company, at $46,931.
-
1982
Converted by 1982.
-
Aug 1982
Building use: apts.
-
May 1983
Additions alterations or repairs.
-
Sep 1990
Parapet.
-
Jun 1993
1 fully partial basement of vietnam ii restaurant sprinkler.
-
Jan 1999
Temp.repairs to ornamental soffit at roof line.
-
Jun 2001
Umb-seismic retrofit works, general procedure(metal collectors and steel frames).
-
Jun 2001
Closing of doors to abandoned elevator with layers.
-
Apr 2003
Umb special procedure.
-
Jan 2009
Install fire system. 2-pcl 460, 1-pcl 300.
-
Mar 2014
Comply with ord 029-13 installing grab bars in public bathroom.
-
Apr 2014
Renewal of permit application 201211023465 and complete work.
-
Aug 2014
Repair cracked wall with epoxy as recommened by santos & urrutia structual engineers, letter is attached for remedy of complaint #201344661.
-
Aug 2014
To make minor repairs of sheetrock and paint in the retail space. 160 sq. feet of sheetrock patching.
-
Mar 2015
3rd and 4th floor: remodel eixsting bathrooms (4-1/2 bathrooms) to comply with nov # 201524571. four and 1/2 bathrooms total (2) on 3rd floor and (2 -1/2) on 4th floor. work in kind. n/a maher ordinance 155-13.
-
Jul 2015
Remodel bathroom on 1st floor above ground. to comply with nov # 201524571. existing light and window to remain. no change. no walls to be moved / no structural.
-
Apr 2016
To replace windows in the hallways to comply with nov 201608152 and also to repair 3 stairs & repair hand rails, install 26 guage stell, galvanized sheets in the garbage room, items to be corrected 3, 4, 5, 9, 21.
-
Apr 2016
Like for like voluntary fire system replacement with new control panel, smoke det. and pull stations at the same location, tie-in existing bells to new panel. install new monitor modules to connect existing waterflow and tamper switches to new panel.
-
Feb 2018
To comply with nov# 201830391 items # 2, 3 & 14, nov# 201835782 items # 2, noc# 201835781 items # 3, 5 & 6, repair or replace kitchen cabinets & counters also to repair or repace laminate flooring & r & r tile in bathrooms in 14 units.
-
May 2018
To repair a broken piece of sheetrock in the basement ceiling an walls to comply with nov #201850491 item #7 and item #8 on 2nd floor.
-
Jun 2024
To comply with nov 202423261. remove and replace acoustic ceiling damaged by water leak. non load bearing wall to be removed and put back. remove and reinstall kitchen hood. replacement of wood front entry dbl door in kind.
-
Apr 2025
In-kind replacement of existing old sliding gate in the front of shop. same size, no additional dimension.
DBI holds 32 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 32. 3 of them are nominal $1 street-space or sidewalk permits. 4 expired or cancelled permits are not shown.
Nearby
- 684 Ellis Street Same street
- 707–719 Ellis Street Same street
- 730 Ellis Street Same block
- 731–743 Larkin Street Same block
- 845 O'Farrell Street Same block
- 851 O'Farrell Street Same block
- 645 Larkin Street Around the corner
- 637–639 Larkin Street Around the corner