Recorded in the city's survey of the Van Ness Avenue automobile corridor as built for use as an auto showroom. A small showroom decorated with brick ornament, in the manner of 550 Van Ness Avenue two years earlier. It sold new cars for only a few years.
-
Jun 1988
Reinforce parapet & roof.
-
Jul 1988
Installation of resturant/seismic of building as per plans.
-
May 1989
3ea kitchen grease hoods type 1.
-
May 1990
3 ea kitchen grease hoods.
-
Sep 1991
Enlarge mezzanine floor.
-
Nov 1991
Additional mezzanine surface struct. interior relocate stair.
-
Dec 1991
Erect sign.
-
Feb 1993
Int.tenant improv. not structural. electrical/plumbing/partitions.
-
Jul 1993
Install canvas over steel tube frame awnings.
-
Sep 1994
New bakery and take out counter, relocation waiting station.
-
Mar 1995
Relocate entry to van ness/new storefront/ramp at entry.
-
Sep 1995
To erect electric sign.
-
Dec 1996
Shoring/underpinning.
-
Dec 2002
Replace kitchen equipment add a 3 compartment sink to comply with health code & modify a room in the.
-
Mar 2003
To erect electrical sign.
-
2010
Evaluated in the city's survey of the Van Ness Avenue automobile corridor and given California Register status code 6Z — not individually eligible for the California Register.
-
Aug 2010
Obtain a building permit for sign located at 690 van ness ave as required by sign i.d number "orig 240" per n.o.r. dated may 5, 2010, block and lot number #0763/012.
-
Apr 2011
Fire damage demolition permit only. remove drywall on different area of wall & ceiling.remove lights. remove metal studs. remove 3/4 sheating. remove carpet. remove doors jombs and baseboard. remove glass countertops. remove tile floors. remove insulation. no construction under this permit.ab017.
-
Sep 2011
Fire repair. rebuild to pre-fire condition (shell only). install 3 complete toilet rooms. fire sprinklers, fire alarm (monitoring) and fire suppression system on separate permits. t. i. demolition completed under permit application 2011 0411 3848. revised to core-shell condition. tenant build back sep permit.
-
Mar 2012
Install new sprinkler system through-out building per nfpa 13 with new 2" fire service off of turk st.
-
Jun 2012
Interior tenant improvement to finish fire repair under 201109164816. new partitions, equipment, mechanical, plumbing and electric work.
-
Sep 2012
Ansul hook up. ti under 201206223284.
-
Apr 2025
Tenant improvement limited to upgrading existing toilet facility to full ada compliance. no structural or exterior work. deferred mechanical, electrical, plumbing and alarm.
-
May 2025
Perform ordinary maintenance to general advertising sign as specified in attached engineering plans, in accordance with planning section 604.
-
Jun 2025
Modification of an existing fire sprinkler system for tenant improvements. add (4) new fire sprinkler heads to restroom stalls. ref permit application 202504083907.
DBI holds 45 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 45.
Not yet documented: the architect and builder and the early tenants. Submit an update