840 Van Ness Avenue
Tenderloin · San Francisco, CA 94109
Permit history
-
Feb 1982
Additions alterations or repairs.
-
Jun 1990
Convert existing ground floor apartments to office space.
-
Mar 1997
Umb seismic upgrade.
-
Aug 1997
Remodel bathroom change kitchen cabinet for all units.
-
Sep 2000
Wireless telecommunications facility install one 18" omni antenna.
-
Oct 2007
Reroofing.
-
Jan 2008
Six units. kitchen and bath remodel. no structural work. no lighting work. replace cabinet, counter tile kitchen. replace vanity, tile, toilet (sink faucet).
-
Jan 2008
Six units. kitchen and bath remodel. no structural work, no lighting work. replace window in bathroom lightwell, n ot visable from street. kitchen: replace cabinet, counter tile & sink faucet. bathroom: replace toilet & vanity.
-
Feb 2008
Seismic upgrade for lateral system - new holdowns and shearwalls. two units level: repair & reframe floor joists.
-
Mar 2008
Work on apr#106 +#503. kitchen & bathroom remodel. no structural work. no lighting.
-
May 2008
Work @ two units only. kitchen & bathroom remodel. remove & replace cabinet, counter, floor & wall tile. no structural work. no lighting work. replace bathroom window in the lightwell.
-
Jun 2008
Two units. kitchen & bathroom remodel. no structural work. no lighting work. replace cabinet, counter, floor & wall tiles.
-
Jul 2008
One unit-408 kitchen and bathroom remodel. no structural work. no lightening work. replace cabinet, counter floor and wall tile.
-
Aug 2014
Stucco repair & concrete, replace in-kind & repair as per nov#201478571 & 201384907 to comply with 201481831 front of the building.
-
Jun 2015
One unit - remove kitchen & bath cabinets. install plumbing & electrical to new existing locations. install cabinets, counters, fixtures. provide vinyl flooring or redo hardwood. paint apartment.
-
Feb 2016
One unit: kitchen & bathroom remodel. new fixtures only no structural work.
-
Jul 2016
One unit: kitchen & bathroom remodel. as like, new fixtures.
-
Aug 2016
One unit: relocation of kitchen/bedroom/bathroom.
-
Oct 2016
One unit: kitchen and bathroom renovation/relocation.
-
Dec 2016
Site permit to add two accessory dwelling units to the basement per ordinance no.162-16.
-
Jan 2017
One unit: kitchen/bathroom renovation, using current layout/no structural changes.
-
Feb 2020
One unit: kitchen & bath remodel. no structural/exterior work req. no change to wall layout. all work within unit. no fire alarm or sprinkler work req. one unit only.
-
May 2020
One unit: kitchen and bath remodel. new cabinets, countertops and fixtures. no structural, no exterior work. no change in existing layouts or wall modifications/infilled. all work within unit. no fire alarm / sprinkler work req.
-
Dec 2020
Upgrade existing fire alarm system to comply with sffc section 1103.7.6.1 and include sprinkler monitoring. ref permit application 2016.1221.5553 ref sprinklers # 2020.0110.1624.
-
Aug 2022
One unit only: kitchen and bath remodel. no structural/ no exterior no change to wall layout. no fire alarm or sprinkler work req.
DBI holds 63 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 63. 1 of them are nominal $1 street-space or sidewalk permits.