325–329 Kearny Street
Union Square · San Francisco, CA 94108
Permit history
-
Apr 1983
Additions alterations or repairs.
-
May 1986
Work is to be tenant improvement on area of less than 1500.
-
May 1986
Demolition of non-bearing single wall wood partition.
-
Jun 1986
Install a kitchen hood, duct work, blower & make up air unit.
-
Jul 1986
Installation of canvas awning with graphics.
-
Oct 1988
Installation of new kitchen hood connecting exhaust duct.
-
Feb 1989
Install duct, kitchen hood fine suppression system.
-
Aug 1991
Reroofing.
-
Apr 1995
Comply with umb ordinances.
-
Jun 2000
Change retail store on street level into a pizza slice to go store.
-
Aug 2005
Remove all furnitures & demolish existing nonbearing partitions; tenant improvement permit will be follow.
-
Sep 2005
Convert portion existingbeauty salon into acupuneture doctor's office&acupressure treatment health ctr.
-
Oct 2005
Revision pa3200509193240 which is under construction. rearrange hair salon and acupuncture office at 2nd & 3rd fl.
-
Jun 2009
Upgrade fire suppression system only in kitchen.
-
Mar 2012
Add a shower & relocate laundry room on 2nd floor. relocate electrical panel. add 2 showers at 3rd floor. all mechanical, plumbing & electrical fixtures will remain except at new shower rooms.
-
May 2012
Remove and replace existing sidewalk with new. remove existing sidewalk with new, remove existing rusted steel beams below sidewalk and replace with new steel beams and steel channels and support with steel pipes with conc. footing.
-
Jan 2016
Demolish storage loft, service counter. build new service counter. alter basement to add walk in refrigeration and new office. bring everything up to current sfdph requirements.
-
Apr 2016
Added lighting/title 24 work to previous permit #201601257897.
-
May 2016
Ul 300 fire system coverage for new kitchen equipment. ref pa 2016-0125-7897.
-
Aug 2018
Demolish non bearing partitions. replace bath fixtures. replace e stair guardrail. soft demolition at 2nd and 3rd fl.
-
Jul 2019
Interior t.i. replace existing bathroom fixtures replace existing stair guardrail, replace 3rd fl. ceiling install new lamnate floors.
-
Oct 2019
Remove existing roofing penthouse. install 3 new skylights and roof.
-
Sep 2020
Reinforce existing roof.
-
May 2023
Reroofing. no tearoff, overlay system.
DBI holds 33 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 33. 3 of them are nominal $1 street-space or sidewalk permits.