901 Rankin Street
Store building · Bayview Hunters Point
-
1948–1952
The main building went up between 1948 and 1952: six one-story, front-gabled volumes of light steel frame clad in stamped steel, erected as a pre-engineered Butler Building, a rigid-frame type common in the 1940s for utilitarian and military uses.
-
1948–1956
The structures have housed a radio shop, a machine shop, a paint shop, cable storage, a warehouse, a garage and offices, and the yard north of them was used for parking, traffic-signal storage and public-safety and telecommunications trailers; by 2011 the site held city offices, for the Department of Technology and the Municipal Transportation Agency.
-
Nov 1994
New building (offices).
-
Apr 1997
Establish a 74' grd-mounted microwave antenna struct.
-
Feb 1998
Provide outdoor equip pad for mecanical units, radio tower.
-
Apr 2003
Interior remodel of city owned shop, one level, 4750 sq/ft. function technical repair & installation.
-
Apr 2013
To erect 2 stories, no basement, commercial warehouse.
-
Aug 2013
Demolish 1 story, type 2, warehouse building.
-
Mar 2014
Install open web steel joist on the property at 901 rankin street. compliance with maher ordinance no.155-13 not required. excavation less than 50 cu yd. shop drawing submittal reference to permit application 201304043755.
-
Jul 2014
Installation of 6 stairs including rails and landing. 4 interior stairs and 2 exterior stair. each stair is from the ground floor (first floor) to the second floor. refernce permit 2013-0404-3755. maher-compliance with ordinance no.155-13. not required.
-
Jan 2015
Interior ti @ 901 rankin st for a produce distribution center, general demolition & construction of interior partitions within warehouse & office.for architectural work only, refrigeration, racking, fire sprinkler & fire alarm under sep submittal. mep, dock leveler & conc infill design under sep permit.
-
Feb 2015
T.i. for warehouse & office use. general demolition & construction of interior partitions, new int doors and int windows. install windows in existing dock openings for architectural work only. refreg, sprnklers, storefront, structural, fire alarm under seper. submittal. n/a for the maher.
-
Feb 2015
Insulated metal panel scope: (1) new walk in freezer with raised insulated floors and (2) new walk in coolers in existing warehouse space. refridg scope: (3) new roof-top mounted condensing units and (1) new evaporative fan cooling units. ele scope: (1) new ele panel, wiring for refridge unit underflr heat.
-
Apr 2015
1st floor: add 85 new "dry pendent" sprinklerd into new 10'-0" high cooled, processing & regridgeration room. fire sprinklers are existing in complete warehouse. maher - not req'd ref t.i. 201502259306.
-
May 2015
Construction of 5 temperature controlled rooms on 1st floor within warehouse area. this is a deffered submittal for permit application 2015.0123.6530. n/a maher ordinance.
-
Aug 2015
Modification of existing warehouse for new tenant. relocate uprights for new walls & add dry penddant for new freezers & rerigerators. references appln #201501236530, 201504224260.
-
Oct 2015
Sprinkler t.i. mollie stone section of warehouse. swap out overhead sprinklers, new rack sprinklers system addition (33 heads). new refridgeration improvements (15 heads). maher na.
-
Oct 2016
2nd floor: demolition and construction of new walls, doors and windows to provide a commercial kitchen at the good eggs tenant space. a dry storage & snack area will also be constructed. new finishes & new lighting will be provided in a portion of the space. mep/fire/life saftey under sep permit maher na.
-
Jun 2018
Installation of walk in coolers and freezers for distribution center.
-
Aug 2018
Sprinkler ti for new walk in coolers/freezers 6000 sq ft to accomodate new high piled stroage, limited to 19 feet high up to class iii commodity only. no class iv or plastics storage allowed. 736 gpm @ 48 psi plus 500 gpm hose = 1236 gpm demand. maher na ref permit application 201806121673.
-
Feb 2022
Install high piled storage racks of 800 linear feet 16' high racks equals to 10, 618 sq ft at the g/f.
-
May 2022
Install new walk in cooler. revision to permit application 201806121673.
-
Jun 2022
Installation of 2 new walk in cooler in existing produce warehouse.
-
Aug 2022
Install 59 new dry pendant fire sprinklers as needed.
DBI holds 58 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 58. 2 of them are nominal $1 street-space or sidewalk permits. 2 expired or cancelled permits are not shown. The produce-market environmental review dates the buildings here to 1948–1952 in its project description and cultural-resources chapter, but to 1948–1956 in its hazards chapter.