Permit history
-
Feb 1984
Reinforcing work for parapets.
-
Feb 1984
Corrective reinforcing work for parapets.
-
Sep 1984
Install new accoustic ceiling newlight fixtures.
-
Jan 1989
Reroofing.
-
Dec 1994
Reroofing.
-
Mar 1996
To comply with umb ordinance(separate permit for 801 kearny ).
-
Jul 1996
To comply with umb ordinance.
-
Feb 1997
Add mezzanine above ground floor at rear.
-
Mar 1997
Remodeling and one partition wall addition.
-
Mar 1997
Reroofing.
-
Oct 2010
New full service restaurant remodeling: install new handicap toiletss bar counter. service counter, kitchen equipment. two type-1 hoods & adding additional square footage to existing building. as per plan. mep under separate permit.
-
Oct 2010
Office remodeling: install new handicap toilets @ existing office area. as per plan. mep under separate permit.
-
Jan 2011
Upgrade floor framing, no lateral work ( previously upgrade per permit application 9604557.
-
Aug 2011
Revision approved #201010283973 remodel commercial space to dining rm. install bar counter & stairway @ 2nd. floor. (restaurant) relocate kitchen to basement from ground floor. as pe plan (fire extinguising system, fier sprinkler syste, mep permit under separate permit.
-
Sep 2011
T.i. restaurant: install hood system & energy compliance (fire extinguisher system, under separate permit). ref. appl.#201010283973 & 201108263430.
-
Oct 2011
Install new fire sprinkler system in accordance with nfpa 13 for a new restaurant, 109 sprinkler heads; and new 4" underground.
-
Dec 2011
Revision for tenant improvements under permit #201108263430. pg &e meter locations. install new kitchen equipment, new refrigeration, new counters for accessiblity.
-
Feb 2012
Install sprinkler monitoring system including 1 facp, 1 pull station, 1 smoke detector, and monitor modules for water flow, tamper, duct detectors, and ansul system.
-
Jul 2012
Install new fire suppression system for kitchen hood and duct.
-
Feb 2013
Reroofing.
-
Aug 2015
Soft demolition of an existing full restaurant to demolish non-bearing wall, counters, workout tables, and hood system per ab- 017. existing fire sprinkler system ceiling light fixtures plmg fixtures and hvac system to remain. n/a for maher.
-
Mar 2016
Relocate existing entry and replace front windows as per plan. the proposed door and windows will match the existing storefront system. finish with matching materials.
-
Mar 2016
Interior remodeling to existing restaurant space. install new dumbwaiter. work stations and relocate existing hood as per plan. ref permit application 201108263430.
-
Jun 2016
Alteration of existing fire suppression system for new changes or appliances.; maher n/a.
DBI holds 37 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 37. 6 of them are nominal $1 street-space or sidewalk permits.