399 Fremont Street
448-unit apartment building · East Cut
-
1906
Multi-storey working-class dwellings occupied this ground through the last three decades of the nineteenth century; everything on the site was lost in 1906. The present building dates from 2016.
-
1929
The Hjul Building, permitted on 4 September 1928 and finished in 1929, stood on this site: a two-storey concrete-framed industrial loft of some 46,500 square feet, later converted to offices. It was the second building on the site after 1906. The present building dates from 2016.
-
Sep 1991
Reroofing.
-
December 14, 2000
The City Planning Commission approved a residential care facility for seven or more persons at the site.
-
Apr 2002
Reroofing.
-
2004
The Planning Department concluded that the warehouse then at 375 Fremont Street, on this site, warranted California Register listing for its unusually vertical, fine-grained facade, reversing a consultant's finding that it was not a historical resource. The present building dates from 2016.
-
January 6, 2005
A two-story, approximately 46,500-square-foot office building, the Hjul Building, stood at the property. The present building dates from 2016.
-
January 6, 2005
The Hjul Building was constructed in 1929 as an industrial building and subsequently converted to office use. The present building dates from 2016.
-
July 21, 2005
One existing two-story building stood at the property. The present building dates from 2016.
-
July 21, 2005
The 375 Fremont Street building was constructed in 1929. The present building dates from 2016.
-
October 6, 2005
The City Planning Commission certified the Final Environmental Impact Report for the 375 Fremont Street project.
-
October 6, 2005
The City Planning Commission approved the conditional use authorization for a 250-foot-tall, 28-story residential project with approximately 225 dwelling units at 375 Fremont Street, as modified. The present building dates from 2016.
-
May 2006
Erect 42-story, 3 basements, 452 dwelling residential with parking building.
-
Feb 2012
Shoring along property line for excavation of lot at 333 fremont (under appln #201202073744).
-
Nov 2013
Excavate, shoring, soil nails.
-
Jan 2014
Tower crane including foundaion and tie-ins. (compliance with ordinace no. 155- required. route to dph.
-
May 2014
Install new 6" underground fire service off of 12" main on harrison, ref.app# 2006-0516-1774 s-10 sprinkler/standpipe submnittal.
-
Sep 2015
163 evacuation signs. basement, 1st, 2nd, 3rd fl through 43rd fl.
-
2016
Built.
-
Feb 2016
Tenant improvement to add grease duct at retail space; maher n/a.
-
Jun 2017
Interior tenant improvement construction of full service restaurant including bar, kitchen, and dining rm. lighting electrical, plumbing, mechanical work new restrooms.
-
Feb 2018
New fire alarm devices in restaurant that are going to be connected to existing building fire alarm system. ref #201706169633. maher na.
-
Feb 2018
Add pendent sprinklers at ti in the area of work. ref #201706169633, maher na.
-
Feb 2019
Reapir drywall using 5/8" type x due to water leak. flood cuts up 2' tall corridors on the 3, 4, 6, 7, 8, 9th floors. units: 702, 601, 603, 302, 301, 303. repairs are approx 1600 sq ft. no stud at existing wall will be cut or replaced.
-
Jul 2024
To comply with nov# 202426256 item#1: drywall removal and replace one unit (40 sq ft), 3407 (25 sq ft), 3507 (13 sq ft), 3508 (2 sq ft), 3706 (58 sq ft), 3707 (28 sq ft), 3907 (42 sq ft), 3607 (8 sq ft), drywall 5/8 like for like insulation like to like.
-
Jun 2025
Restaurant remodel, interior non structural partitions, new millwork, new equipment.
-
Jul 2025
Remove existing barbecues and sink. demolish existing barbeques, counter and sinks. re-build new proposed barbeque counter, maintaining existing power, gas, and connections. install new barbeques (2 total) install new sinks (2 total). deferred mep). no plumbing fixures.
-
Sep 2025
Fire only show existing kitchen appliance layout for ansul system.
-
Jul 2026
One unit: install insulation and drywall, install baseboards, carpet, apply texture and paint, 5th floor hallways, install insulation and drywall, apply texture, one unit: install insullation and drywall apply texture and paint, one unit: fill holes, install baseboards, caulk and paint.
DBI holds 60 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 60. 7 of them are nominal $1 street-space or sidewalk permits. 6 expired or cancelled permits are not shown.
Nearby
- 350 Fremont Street Same street
- 333 Fremont Street Same block
- 325 Fremont Street Same block
- Coffin-Reddington Building Same block
- 345 Folsom Street Same block
- 434 Harrison Street Around the corner
- Sailors' Union of the Pacific Building Around the corner
- 400 Beale Street Around the corner