Permit history
-
May 1990
Replace toilet rooms on 2nd and 3rd floors.
-
Dec 1991
Reroofing.
-
Apr 2001
Seismic reinforcement.
-
Apr 2004
To erect electric, roof & single faced sign.
-
Apr 2004
To erect electric, roof, single faced sign.
-
Nov 2004
Erect sign for electric, roof single faced.
-
Nov 2004
Erect sign for electric, roof single faced.
-
Aug 2006
Conversion and adaptive re-use of two existing buildings to residential use with 40 dwelling units with off-street parking, and approx. 10, 000 gross square feet of ground floor commercial use.
-
Aug 2012
Seismic work of (2) existing buildings that occupy a single legal parcel. work to include demolition of non-structural & structural elements. installation of new elevator, new fire exits & new utilities. core & shell only. ti under separate permit.
-
Apr 2013
Installation of new fire sprinkler system for entire building with new 8" fire service.
-
Apr 2013
Compliance/w maher ord. #155-13 not req'd. excavation less than 50 cu ft. new roof deck on the existing roof of the 1 story portion of building. work to include new lobby serving roof deck, exterior walkways & stairs that connect the roof deck to exit stairs.
-
Apr 2013
Replace existing wood columns supporting the billboard with steel columns and strengthening the existing wood roof beams to support future mechanical equipment loads.
-
Jun 2013
New fire alarm sys for core&shell-control panel/dialer, area smoke detectors, smoke/duct detectors for damper, wtr flow/valve tamper modules, remote annunciator, smoke/heat detectors for elevator, smoke/duct detectors for ahu¬ifn appliances&boosters.ref 2013/12/06/3494.** maher ord compliance not req.
-
Aug 2013
In-fill of an existing floor opening & removal of stairs connecting the basement & ground floor spaces. the construction of a new opening & stairs within the same space. no exterior work.
-
Sep 2013
Shell strucural work on 1 story portion of building. remove selected columns from basement.
-
Dec 2013
Warm shell hvac- garage exhaust. warm shell plumbing care bathrooms. shower. reference app#201208157486 r1. ** maher: compliance with ordinance no# 155-13 not required **.
-
Dec 2013
T-i in basement, ground floor & mezzanine. non structural partitions, ceiling lights, millwork. sprinkler on seperate permit. -maher- compliance with ordinanace no.155-13.not required.
-
Dec 2013
3/f: full floor tenant improvment. non structural partitions millwork/finishes. mep, sprinklers, fire alarm on separate permit.
-
Dec 2013
2nd floor: full floor t.i. non-structural partitions finishes, millwork. mep, fire alarm and sprinklers on seperate permit.no soil disturbance. compliance with ordinance no. 155-13 not required.
-
Apr 2014
In basement and 1st floor - fire sprinklers for t.i. basement level: 21 add uprights, 86 add pendants, 1st floor: 10 add uprights, 36 add pendents. ref. appl. 201312194664. maher n/a.
-
May 2014
Provide & install fan coil unit at 2nd floor, install ventilation duct from ventilation make up unit to each fan coil, install refrigerant piping for new fan coil. ref #2012.0815.7486. compliance with ordinance maher #155-13 not required. interim control n/a.
-
Jun 2014
3rd floor: electrical work for t.i. n/a for the maher ordinance #155-13.
-
Jun 2014
Provide and install fan coil unit at 3rd fl ventilation duct from ventilation make up air unit to each fan coil, refrigerant piping for new fan coil, install exhaust fan, and transer air for it room ref 201312234857 maher 155-13 not required.
-
May 2019
Interior non-structural demolition at existing reception area on ground fl. construction of new coffe bar with ada. mep and life safety under sep permit. improvements of the front door.
-
Apr 2021
Modification to existing restrooms as revision to approved permit 201208157486. remove existing toilet partition. reinstall new. remove existing non bearing wall and replace with new wall to provide minimum clearance in front of water closet.
DBI holds 57 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 57. 8 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the developer and the early tenants. Submit an update