236 Monterey Boulevard
Building · Glen Park
-
December 1978
The Merrill Conservatory here was partly demolished under a demolition permit issued in error, until the Planning Commission barred further demolition.
-
December 6, 1978
The Board of Permit Appeals upheld the revocation of a demolition permit for the building at 236 Monterey Boulevard.
-
January 25, 1979
The City Planning Commission unanimously refused to reclassify the lot from RH-2 to RM-1 (Resolution 8162).
-
March 1979
The Park and Recreation and Planning Commissions jointly recommended that the city acquire the partly demolished conservatory, through the Trust for Public Land.
-
Aug 2008
Restoration &rehab ofexistinghistoric conservatory structure&grds. selective demolition, conservatory shoring, grading, excavation.concrete paving, curb ramp accessible, landscape, tree transplanting, irrigation, fencing.the conservatory will be seismically strengthen & restore with period material&finishes, mechanical/electrical up.
-
Feb 2009
Install overhead fire sprinkler system, 16 heads.
-
Jun 2009
Fire sprinkler system 200902273086.
2 nominal $1 street-space or sidewalk permits are omitted from the timeline. 1 cancelled permit is not shown.
Nearby
- 230 Monterey Boulevard Same street
- 258 Monterey Boulevard Same street
- 297 Joost Avenue Same block
- 230 Joost Avenue Around the corner
- 216 Joost Avenue Around the corner
- 151 Mangels Avenue Around the corner