612–694 Grove Street
Hayes Valley · San Francisco, CA 94102
-
1968
Ammel Park Co-op, one of the co-operative apartment complexes African American groups built in the A-2 redevelopment area with ILWU help.
-
Jan 1986
Construct a chainlink fence.
-
Nov 1993
Reroofing.
-
Nov 1993
Reroofing.
-
Nov 1993
Reroofing.
-
Nov 1993
Reroofing.
-
Nov 1993
Reroofing.
-
Nov 1993
Reroofing.
-
Nov 1993
Reroofing.
-
Feb 2014
To comply with nov. #201446012. fire restoration repairs due to fire in living room at one unit. no structural damage was caused. entire unit was completed gutted (drywall/insulation) due to smoke damage.
-
May 2019
Perform stucco demolition @ up to 32 locations of approx 2'x2' each, throughout complex, repairs to be made in-kind.
-
Jan 2021
Building #4: waterproofing repairs of patios & decks & replacement sliding glass doors. replace selective windows at ground floor. all repairs to have replacement materials like for like.
-
Dec 2021
Dry rot repair in exterior walls, behind stucco plaster. 2 locations, all repairs to have replacement materials like for like. invisible from street.
-
May 2022
Reroofing.
-
Oct 2022
Comply with nov #202292522. vehicle crash mitigation temp shoring of 2nd fl & bracing @ laguna st & fulton st. removal of stucco & sheathing around lower front facing window @ 749 laguna st & 6' around corner of fulton st. repair all broken framing from collision. remove of shoring. r/r window w vinyl.
-
Jan 2026
Commencement of work not started under previously approved permit. 202210134274.
-
Jul 2026
Building 3 one unit: repair dry rot in kind. exterior side wall. stucco to stucco in this case.
-
Aug 2026
Building #6: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement.
-
Aug 2026
Building #1: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement. addition of two accessible units.
-
Aug 2026
Building #7: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement.
-
Aug 2026
Building #5: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement.
-
Aug 2026
Renovation existing community building. reconfiguration interior space to upgrade the existing bathroom and kitchen to accessible spaces. new windows and refresh of exterior, patching and paint. new playground & community spaces. 2 accessible parking spots & add accessible path.
-
Aug 2026
Building #3: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement.
-
Aug 2026
Building #4: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement. addition of two accessible units. site improvements to provide a compliant accessible path to parking and the public right of way.
-
Aug 2026
Building #2: in-kind window replacement. exterior repairs, including partial stucco replacement/repair and paint. roof replacement.
DBI holds 36 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 36. 4 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early residents and the date of the last recorded sale. Submit an update