1580–1598 Market Street
72-unit apartment building · Hayes Valley
-
1917
Built.
-
1917
Miramar Apartments, designed by G. Albert Lansburgh.
-
Jun 1985
Parapet code work.
-
Aug 1985
Barricade around project.
-
Sep 1986
Gas meter room, entry to hotel, new stair.
-
Jun 1987
New wall separating kitchen from public area, new ramp/floor.
-
Feb 1989
Store no 2 remodel to lobby lounge use.
-
Sep 1996
Install sidewalk handicap ramps.
-
Aug 2002
Seismic upgrade of structure, new doors, partitins, electrical. mechanical, & plumbing. int. remodel of lobby, new.
-
Mar 2003
G/f- expanding existing restaurant into an existing adjacent retail, mechanical/lighting seperate permit.
-
Apr 2003
Furnish, program & install final test fire alarm system. 6/fl & bsmt.
-
Apr 2003
Demolition exist spkr. sys@ basement & grd floor. & re design basement thru 6th fl for fully sprinklered.
-
Jan 2011
To comply with nov #201082028: repair water damage, remove & replace drywall finish, carpet, paint and ceiling for five units & lobby. provide 1-layer 5/8" type x gyp bd ea face at wall separate dwelling units & corridor, 2-layers 5/8" type x gyp bd at ceiling. no wall relocation.
-
May 2011
Change of use from restaurant to bakery - interior non bearing walls. new ada bath. new flooring, update existing kitchen area, new hood, painting for new bakery.
-
Jul 2011
Remodel existing commercial space to cafe. add 1-unisex bathroom, counters, built-in benches & kitchen equipment @ prep. area. mep under separate permit.
-
Jul 2018
Reroofing.
-
Aug 2024
To comply with nov# 202425986: repair brick ponywall - replace store front in kind.
-
Apr 2025
Two units: like for like interior finishes non structural, no changes to fire rated assemblies or room layouts. interior repair of lobby, gym, bathroom and kitchen due to water damage. scope includes drywall, paint, ceiling tiles, flooring, cabinetry, plumbing fixtures.
-
May 2025
The project is the rehabilitation of a single east facade of an existing 6 story historic brick masonry building built in 1911. the proposed project involves exterior envelope repairs, including: masonry repairs replacement of existing masonry opening infill & treatment of existing structural members.
-
Dec 2025
Ed13-01 priority: renovation to units of 100% affordable housing: voluntary seismic upgrades, accessibility upgrades, mep upgrades, facade repair, relocation of amenitie4s to g/f from the basement and interior repair.
DBI holds 56 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 56. 4 of them are nominal $1 street-space or sidewalk permits. 7 expired or cancelled permits are not shown.
Nearby
- 1576 Market Street Same street
- 1601 Market Street Same street
- 98 Franklin Street Same block
- 1540 Market Street Same block
- 53–55 Oak Street Same block
- 1500 Market Street Same block
- 1 Franklin Street Around the corner
- 23 Franklin Street Around the corner