1632 Market Street
Hayes Valley · San Francisco, CA 94102
-
1911
A concrete loft building cited as the type example of the industrial lofts of the Market Street corridor.
-
Jan 1982
Additions alterations or repairs.
-
Apr 1983
Work consists of dividing floor into large storage areas.
-
Apr 1984
Fire wall, two doors leading into worshop.
-
Mar 1985
Pour concrete pad on existing 16" concrete roof.
-
Apr 1985
Erecting a dividing wall.
-
Jan 1993
Repair hair-line cracks in building walls.
-
May 2000
One-stop, wireless telecommunications facility, micro cell site consisting one 18" omni antenna.
-
Jul 2000
One-stop, wireless telecommunications facility, revisio to #200005301325, rev to structural support ret.
-
Sep 2002
Alter existingelevator, incl elevator recall to meet accssbily reqmt; incl fire alarm.
-
Feb 2003
As-built drawing's to reflect life safety revisions.roll-up fire doors abandon in place.
-
Sep 2003
To erect electrical sign.
-
Oct 2003
To erect double faced electric sign.
-
Apr 2006
During demolition of 55 page street, it discover 43 page & 55 page street share the same exterior wall. this permit is for exterior wall per plan.
-
Apr 2009
Replace existing storefront with new storefront in existing opening, including new door (secondary entrance/exit) and steps. remodel existing bathroom for accessability (ada) compliance.
-
Jun 2011
Remove all sprint nextel wireless equipment site will be repair to original condition.
-
Jun 2014
To obtain final inspection for work approved under permit application 201106208479, all work is complete.
-
Nov 2014
Change use from a retail space to a pilates studio. change double door to single door at entrance per plan. new t.i. new exercise room.
-
Jul 2015
Install a new canvas awning over storefront.
-
Jul 2015
Custom hand paint logo on existing canvas awning. non-structural and non electrical. refer to ap # 201507131252.
-
May 2018
To obtain final inspection for 201411131447.
-
May 2018
Remove non load bearing partition and patch repair flooring. relocate basin in bathroom to meet accessible requirements.
-
Dec 2018
Install electric wall mounted projecting double faced sign "storage".
-
Dec 2022
For compliance with abe program 56-16 (abe no. 201911228664). ada barrier removal at 3 existing commercial ground fl tenants - unit a, b, c per sfdbi abe program. scope of work to include: relocating existing tenant entry doors & renovaion of existing unit b unisex restroom to be accessible.
2 nominal $1 street-space or sidewalk permits are omitted from the timeline.
Not yet documented: the architect and builder and the early tenants. Submit an update