Installed 2006. The 74-by-40-foot glass curtain wall uses prismatic glass fins with dichroic glass strips that project colored light onto the facade and into classrooms, fulfilling San Francisco's 1% for public art requirement; architect for the addition was Perkins + Will and the glass was fabricated by Lenehan Architectural Glass.
Permit history
-
Jun 1991
Parapet.
-
Nov 1996
Provide drywall to studs to create 1-hr corridor, doors, frame.
-
Mar 1997
To verify for proper occupancy class.
-
Feb 1999
Provide angle iron braces & anchors to parapets & roof.
-
May 2002
Parapet bracing.
-
Oct 2002
Erect 6 story educational building.
-
Feb 2004
Shoring & underpinning of existing 50 oak. all work is temporarily and will be ermoved once new stru.
-
Mar 2004
Installation of underpinning & tiebaccks along the existing hickory and oak st. foundation walls.
-
Apr 2004
Rev. appl#200210098630 for duct & mep in foundation.
-
Oct 2004
Install new fire sprinkler system at all floors.
-
Feb 2005
Erect: single faced, existing awing/marquee canopy, non-illuminated new sign.
-
Apr 2005
Generator operating permit - reference- permit application 2002/10/09/8630.
-
Apr 2005
New fire alarm consisting of smoke detectors, strobe, speakers, sprinkler monitoring, hvac duct dete.
-
Aug 2005
Streetspace.
-
Feb 2006
Revision to permit application 200210098630-si: )addition of (2) 3 hour walls (non structural) with 3 hour doors at (2) electrical spaces at lower level 2 and lower level 1.
-
Apr 2006
Floors 1 to 6 - supplemental information to 200210098630.-sheet a0.08 project info: filed agreement between sq ft cons of music and adjacent property owner regarding property line windows per admin bulletin 009.
-
Mar 2007
Revision to approved permit application 200210098630 add 4 automatic door openers i leiu of push side clearance at thickend concrete wall per inspectors request.
-
Dec 2007
Accoustial plaster on walls (3 walls) approx 40 ft tall x 60 ft wide @ concert hall ara (1/8" accoustical plaster).
-
Feb 2008
Renew appl#200504139931 for final inspection.
-
Feb 2008
Renew app #200410146799/200703025376/200502105261.
-
Feb 2008
Renew permit applications nos. 200404050426; 200604058316 and 200504119706 for final.
-
Feb 2008
Renew app #200602214988/200402236924/200403128481 for final inspection.
-
Mar 2019
This project will be adding one anchor at a location specified on drawings. the anchors will be at a minimum 18' above grade and include a 1/2" hilti kwik bolt embedded 4" into the buildings concrete facade to hold up string lights over hickory alley.
-
Dec 2025
Installation of voluntary cell communicator + monitor module for supervision of communicator to exist. fire alarm system.
4 nominal $1 street-space or sidewalk permits are omitted from the timeline.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update