364 Page Street
Hayes Valley · San Francisco, CA 94102
-
1929
Built.
-
Oct 1981
Additions alterations or repairs.
-
Jan 2002
Replace kitchen cabinets, sink & countertops one unit. no structural work.
-
Dec 2004
Replace kchn cabnts/replace bth vanity and mefdicine cbnts.
-
Jan 2005
Replace kitchen cabinets. replace bath pedestal in one unit only.
-
Nov 2006
Work @ one unit. replace kitchen cabinets, replace tiles in bathtub enclosure. replace bath vanity. replace bath medicine cabinet. flourescent lighting. one bathroom. 1 kitchen.
-
Dec 2009
One unit. replace bathtub, tiles, vanity. kitchen cabinets. new lighting.
-
Nov 2010
#29- 1 kitchen- replace kitchen cabinets. 1 bath - replace bathtub, lighting to comply with cec 150(k), replace tiles in tub enclosure, no change to exterior, replace vanity & medicine cabinet. no change to windows, door or change of walls.
-
Nov 2013
Replace kitchen cabinets & countertops, replace bathtub & tiles in bathroom, replace vanity in one unit.
-
May 2014
Reroofing.
-
Jun 2015
One unit - replace kitchen caboinets & countertops; replace bathtub & tiles in bathroom; relocate closet; replac4e vanity & medicine cabinets; no structural work; to comply with cec150.0(k)3 & 5.
-
Aug 2015
Soft story retrofit per sfbc chapter 34b "2012 iebc appendix a-4." comliance with mandatory soft story retrofit program, 2013 sfbc sec 34b & 2012 iebc appx a4.
-
Oct 2016
#34 interior renovation to add one unit of studio apartment. turn one unit - 2bed/1bath into 34a with 2 bed/2 baths & 34b studio.
-
Nov 2016
Kitchen & bathroom remodeling, no alteration of walls, windows & doors, one unit.
-
Jul 2017
#8: converting 2nd floor studio one unit in 22 unit building into a one bedroom unit. relocate kitchen and remodel bathoom. electrical and plumbing work to be performed. no structural work to be performed, existing windows to remain. n/a for maher.
-
Aug 2017
3/f #28- convert studio into a one bedroom unit, relocate kitchen & remodel bathroom. electrical & plumbing work to be performed. no structural work, existing windows to remain.
-
Oct 2017
#21- replace kitchen counter tops & all appliances, remodel bath room.
-
Nov 2017
Interior remodel of 1st fl studio one unit. relocate existing kitchen to create 1 bedroom. no structural work or window alteration. plumbing and electrical work to be performed.
-
Feb 2018
Interior remodel of one unit on first. new kitchen cabinets and counters, new bathroom fixtures and finishes. no exterior work. convert studio into 1 bedroom. no sprinkler or fire alarm work.
-
Jan 2020
One unit: interior remodel of 3rd floor one bedroom unit. relocate existing kitchen to create new bedroom. convert existing bathtub to shower. no structural or exterior work.
-
Jun 2021
New installation of fire alarm system: (1) fire alarm control unit ifp-75, (1) new wireless communicator, (1) monitor module, (1) power supply, (3) manual pull stations, (9) smoke detectors, (4) wall mounted horn strobes, and (37_ new low frequency sounders.
-
Jul 2021
One unit: interior remodel of 2nd fl. studio, relocate existing kitchen to create new den & laumdery room, no structural or exterior work. bathroom remodel, replace tub with walk in shower.
-
Jul 2021
One unit: kitchen and bath remodel, no change to layout, replace tub with new shower in bath room, kitchen 50sf bath 45sf.
-
Jan 2022
Upgrade existing fire alarm system to comply with sffc section 1103.7.6.1.
-
Sep 2024
One unit convert existing 1 bedroom unit to a 2 bedroom unit. no structural work. no exterior work.
DBI holds 34 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 34. 1 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 350 Page Street Same street
- 380 Page Street Same street
- 340 Page Street Same block
- 384–388 Page Street Same block
- 368 Lily Street Same block
- 308–310 Page Street Same block
- 253–263 Laguna Street Around the corner
- 405 Buchanan Street Around the corner