1400 Geary Boulevard
Japantown · San Francisco, CA 94109
-
Jun 1982
Building use: office/apts.
-
May 1994
Renovate public area of residence facility addit'n restrooms.
-
Jun 1994
To install an emergency generator & tank (9406865).
-
Jun 1995
Addition of new elevator to existing 7 storey building.
-
Aug 1997
Install fire alarm per plans.
-
Jan 2004
Renovate of existing dining rm partial remodel of existing kitchen support area small building addition of 1 story.
-
Apr 2004
Removal of waterproofing concrete planters, paving and landscaping material.
-
May 2004
Phase ii plaza redevelopment waterproofing paving new planters new electrical new plumbing demolition.
-
Mar 2005
Plaza redevelopment phase 3 & 4 parking area. waterproofing, re-paving & grading, new landscaping.
-
Jul 2006
Level b hvac system new 1-20 ton split a/c system 2-5 ton split a/c systems for server room.
-
Jul 2007
Floors 3rd thru 25th floors-replace existing pane window frames and glazing with new commerical heavy duty aluminium windows with thermal breaks.
-
Aug 2007
Renovation of existing residents one unit/f, 14/f, 20/f, 21/f, 24/f, 25/f.
-
2009
Recorded in the city's 2009 survey of Japantown as a large-scale Brutalist apartment block and tower, of the kind redevelopment put along the Geary Boulevard corridor in the 1960s and 1970s.
-
Feb 2011
(level "a" - atrium): atrium level being redone. remodel existing restrooms (men & womens). remodel library area, redo fireplace, new mep. sprinklers under separate permit.
-
Sep 2011
Renovation and refurbishing of bedrooms, toilets, shared program spaces, staff areas and corridors on the mezzanine and third floors of existing 26 story steel and concrete building. project also includes the renovation of existing construction in and around a large mechanical shaft on the mezz. & 3rd fl.
-
Dec 2013
Utility upgrade: existingelec. service + equip demolition'd & replaceexistingmain switches & main switch board; newelectrical room @ basement level; newcircuit breaker class switch boards; newplug in bus riser 3rd thru 25th floors; decommisioning ofexistinglaundry room/basement converting to sotrage use.
-
Mar 2016
Equipment & finishes upgrades to existing dining room in multifamily residence building.
-
Aug 2016
Level b - laundry reconstruction project: renovate existing storage room & office area into new commercial laundry facility with assoc clean soiled linen room. an addition of epo switches & trench drains to an existing ele room. fire alarm and sprinkler system revisions under separate application.
-
Jan 2018
Remove and replace h ot water storage tanks and associated flat plate heat exchangers in e level b mechanical room b1.6.
-
Dec 2018
Refurbishment and mino renovation of existing meeting rooms and addociated accessory space.
-
Oct 2019
Renovation of 2 exhaust hoods in the level a kitchen as well as the replacement of an air handling unit. exhaust fan and pollution control unit in the level g mechanical room that serve the level a kitchen and associated dining area.
-
Oct 2019
Renovation of an existing level a resident store room into a fitness center. the relocation of an existing level a staff workroom. and the relocation of resident storage to an area within the level b parking garage.
-
Jan 2023
Replace 196 speakers with new. add 257 speakers, add 2 smoke detectors, 3 speaker strobes.
-
Mar 2024
Reroofing; coating the roof with liquatec roof coating. approx 5500 sq ft.
-
Feb 2026
Installation of new fuel cell equipment with associated structural platform support, plumbing and electrical engineering. all exterior work and no modificationsto existing building or use impacted. loading dock will remain in use.
-
Aug 2026
Replacement of exterior glazing systems throughout the entire facility, including windows, storefronts, entrances & curtain walls.replacement of elevators, traction machines & counterweights withnew cabs, controls & equipment for anewdestination dispatch elevator system.
DBI holds 317 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 317. 14 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early residents and the date of the last recorded sale. Submit an update