21,348 sq ftBuilding area
51,662 sq ftLot area
  1. 1946

    Built as an industrial building, recorded as occupied by Greyhound Lines storage & workshop.

    Showplace Square / Northeast Mission Historic Resource Survey, adopted 2011
  2. Dec 1991

    Site improvement.

    Expired Permit 9123551 $$$ $10,000
  3. Nov 2004

    Erect 1 story post-secondary education building.

    Complete Permit 200411229879 $$$ $700,000
  4. Mar 2006

    T.i. for existing steel framed bldng. previously approved for site and demolition permits (2004/11/22/9873 & 2006/01/10/1832; work includes new partition walls (not full height); new mfgrd bathroom containers - located outside of bldng. new metal roof new lighting & mechanical. fire protection under separate.

    Complete Permit 200603015723 $$$ $150,000
  5. Oct 2014

    Erect a four story office and retail commercial building. compliance with ordinance 155-13 is not required.

    Complete Permit 201410209377 $$$ $52,500,000
  6. Dec 2017

    1st & 2nd floor ti build outs. 1st floor lobby access to elevators and 2nd floor office space.

    Issued Permit 201712186744 $$$ $1,947,035
  7. Dec 2017

    3rd floor ti build out of 3rd floor office space, mep deferred. maher na.

    Issued Permit 201712186749 $$$ $1,918,280
  8. Dec 2017

    4th floor ti build out of wellness center and office space. mep deferred. maher na.

    Issued Permit 201712186750 $$$ $2,124,038
  9. Dec 2017

    3rd floor ti build out of 3rd floor office space, mep deferred. maher na.

    Issued Permit 201712186745 $$$ $1,918,280
  10. Feb 2018

    1st & 2nd floor - mep to support ti 201712186744 maher na.

    Issued Permit 201802151333 $$$ $1,429,345
  11. Feb 2018

    To erect 5 stories, no basement, type iii-b over i-a, 280 dwelling unit building for residential student housing. (r-2, a-2, s-2) maher ordinance comply.

    Complete Permit 201802161503 $$$ $28,600,000
  12. Feb 2018

    3rd fl - mep to support approved architectural. ref #201712186749. maher na.

    Issued Permit 201802161534 $$$ $1,420,000
  13. Feb 2018

    4th floor south - mep to suppor approved architectural ti ref #20171286750. maher na.

    Issued Permit 201802221931 $$$ $1,420,000
  14. Mar 2018

    3rd fl - mep to support approved architectural ref pa 2017-1218-6745.

    Issued Permit 201803012571 $$$ $1,420,000
  15. May 2018

    Suite 7: commercial t.i. includes construction of non-structural partitions ceiling, lighting, mechanical and electrical as well as casework and finishes. n/a for maher.

    Complete Permit 201805048217 $$$ $968,250
  16. May 2018

    Suite 7: construction of mezzanine, accessible lift and stairs in existing core and shell.

    Complete Permit 201805048216 $$$ $500,000
  17. Jan 2019

    Suite 4, "seven stills" - tenant build-out of restaurant and brewery space, restrooms, partitions, non-structural partitions, lighting & finishes. phase 1 permit application 201810152399.

    Complete Permit 201901291477 $$$ $1,500,000
  18. Mar 2019

    Mep reference 201901291477; mechanical new fan coils kitchen exhaust fan, exhaust fans, new fire smoke dampers, lighting power and signal plumbing.

    Complete Permit 201903225992 $$$ $900,000
  19. Aug 2019

    Ste 1, 2 & 6 - commercial tenant improvement including construction of non-structural partitoins; exterior door alterations, lighting, cabinetry & finishes. ample for use pursuant to planning code section 102 with accessory office, gategory g per approved pdr use map-robotics manufacturing.

    Complete Permit 201908158968 $$$ $2,000,000
  20. Aug 2019

    Tenant improvement to allow vacant pdr space suite #3 to alter 11, 180sqft of demised space to accomodate modular commercial kitchens for the delivery made to order. maher na.

    Withdrawn Permit 201908290218 $$$ $1,300,000
  21. Nov 2019

    1st fl - electrical power distribution, branch poiwer, new lighting controls ti. pdr use pursuant to planning code 102 with accessory office. category "g" per approved pdr map/robotic manufacture. ref pa 2019-0815-8968.

    Complete Permit 201911258061 $$$ $750,000
  22. Dec 2019

    Revision to permit application 2018-0216-1503 s3: to include permanent gate at entry to court 2 on hooper; additional permanent gate at entry to court 2 on channel st; and temporary gates out of 184 hooper while court 2 is under counstruction.

    Complete Permit 201912189850 $$$ $300,000
  23. Sep 2020

    Suite #3: construction of mezzanine, accessible lift, stairs in existing core and shell building.

    Complete Permit 202009305592 $$$ $150,000
  24. Nov 2020

    One unit: spec suite build out including construction of rated and non-rated walls, conference & meeting rooms, electrical room, break room, & lighting. existing mezz, lift & stairs approved under permit application 201906113160.

    Complete Permit 202011138886 $$$ $1,000,000
  25. Dec 2020

    Suite 3. spec suite build-out incl construct of rated & non-rated partitions, conference rms, meeting rms, electrical rm, breakrm and lighting. mezzanine permit application 202009305592.

    Complete Permit 202012090608 $$$ $1,000,000
  26. Feb 2021

    One unit: mechanical - 7 new fan coiles, 1 outside air, 2 new exhaust fan, 1 new condension unit, 2 new branch selector boxes. electrical-lighting, paper & signal. ref permit application 202011138886. maher n/a.

    Complete Permit 202102013764 $$$ $400,000

DBI holds 180 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 180. 23 of them are nominal $1 street-space or sidewalk permits.

Not yet documented: the architect and builder and the early tenants. The assessor dates the building to 2008; the city's 2011 survey of Showplace Square and the northeast Mission dates it to 1946. Submit an update