268–278 Alabama Street
Mission · San Francisco, CA 94103
Permit history
-
Mar 1983
New construction wood frame.
-
Jul 1991
Construct parking lot.
-
Jan 2000
Erect a one story warehouse/parking building.
-
Aug 2000
Grading.
-
Feb 2001
Lighting & gas space heater installation.
-
Jan 2019
Interior work, new occupancy retail, arts activities, health services.
-
Apr 2019
Mechanical/ele and plm work only in association with permit application 201901029486 maher na.
-
Jun 2019
Installation of fire sprinklers throughout the building per nfpa 13 and underground per nfpa 24. ref pa 2019-0102-9486 total 88 sprinkler heads.
-
Jun 2019
Installation of new sprinkler waterflow & supervisory system with control unit radio comm. smoke detector & pull station with voluntary notification devices thru-out. ref permit application 201901029486.
-
Dec 2019
Revision to 201901029486. to add a mezzanine level to e building and additional egress to exterior also added.**maher n/a**.
-
Sep 2020
F/a: add new notification devices to an existing control panel. add new relay modules & duct detector for rtu 1+2. ref permit application 201901029486 and #201906183711.
Not yet documented: the architect and builder and the early tenants. Submit an update