325 Sacramento Street
Nob Hill · San Francisco, CA 94111
Permit history
-
Apr 1999
Provide umb retrofit.
-
Sep 1999
T/i install new elevator new stair new bathrm walls doors.
-
Apr 2000
Street space use.
-
May 2000
Restoration of facade replace door provide accessibility instal granite trim and granite ven.
-
Sep 2000
Install fire sprinkler system throughout the building.
-
Nov 2000
Revise to appln 9918636 to eliminate exterior signage canopy exterior lights change bl; dg color.
-
May 2002
Revision to permit application 9918637-new t.i. improvement.
-
Sep 2002
New fire sprinklers at basement, first and second floors.
-
Nov 2002
Revision to existing permit #200205307765/r3 shoring outside property line to be under separate permit.
-
Nov 2002
Sign permit - electric, wall, single & double faced, projecting sign.
-
Dec 2002
Life safety system - modification at 325 sacramento st. baement, 1st & 2nd floor - horn/strobes.
-
Apr 2004
Renew expired permit #200211121221.
-
Apr 2004
Otc alterations permit.
-
Apr 2004
Renew expired permit 9918636/9918637/200008016590.
-
Jun 2005
Retrofit of seismic anchorage for mri equipment on ground fl.
-
Sep 2006
Installed over existing 3 new tube steel frame with 3 new cross i-beam with braces. 8 new post supports for new ts5x2x support frame with 3/4" plate. to accomodate medical equipemtn change. ref: 2002111212201 & 200205307765.
-
Aug 2008
Remove a sign from front of building. no new sign will be installed under this permit. sign was installed under permit application 2002/11/15/1585.
-
Aug 2016
2nd floor only: this project consists of a ti of an existing leased space. the space will be used for medical imaging. the improvements consist of the addition of a new x-ray mammo dexa, ultrasound modalitite. minor mechanical, electrical and structural improvements will take place to accomodate the modalities.
-
May 2020
This project consists of the installation of a new mri magnet, new mechanical support equipment, and structural enhancement for support of new magnet and mechanical equipment.
-
May 2021
Revision to 202005117401 for revised equipment installation.
-
Oct 2022
Modification to existing sprinkler water flow & supervisory system to provide t.i.
-
Apr 2024
Install new fire alarm panel to existing fire alarm system in existing commercial. reference permit application 202210265217.
-
Jan 2025
As-built drawing for 202404119799 per sffd field inspector requirement. add 1 smoke detector above sprinkler monitoring system.
-
Jul 2025
Revision 202501178593-install of a new fire panel and cellular communicator all fire alarm devices shall be new.
DBI holds 30 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 30. 4 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update